Accelerate!
The project in Youxi is in full swing
Hurry up and take a look with the editor~
In the past few days, Taixi Township has been advancing as a whole
County-level rural comprehensive logistics infrastructure construction project
(Cheongnyeong section of the Nakasaka Line)
Construction work
At present, the main project of the project has been completed
?? ??
The Youxi County Rural Integrated Logistics Infrastructure Construction Project (Qingxi Section of the Zhongban Line) officially started on September 28, 2023.
At present, the investment amount is about 32.5 million, mainly including about 14.82 kilometers of excavation and construction, 41 round pipe culvert excavations, 13.32 kilometers of existing pavement cracking and excavation, 9,000 square meters of retaining walls and shoulder walls have been poured, 13.32 kilometers of pavement water stabilized layer and surface layer have been completed (all completed), 1.5 kilometers of asphalt pavement of Qingxi Street have been completed, 10.6 kilometers of ditch pouring have been completed, 12,000 square meters of slope greening have been completed, and 4,500 meters of corrugated guardrails have been installed. 900 meters of concrete guardrails were poured, and 3,000 square meters of ground cover were planted.
Greenery along the road
Asphalt grouting
As-built drawings
In the next step, in order to ensure the completion of the project, ancillary works such as asphalt grouting joints, greening along the line, and marking will continue to be implemented.
Source: Chaxiang Taixi