The construction of Wanzhou Harrier Rock Garbage Transfer Station is progressing smoothly

author:Micro Wanzhou

Harrier Rock Garbage Transfer Station in Wanzhou District

As the most advanced and environmentally friendly garbage transfer station in Wanzhou,

Since the start of construction, it has attracted much attention from the public.

At present, the construction of the whole project is progressing smoothly.

70% of the total amount of work has been completed.

The construction of Wanzhou Harrier Rock Garbage Transfer Station is progressing smoothly

The Harrier Rock Garbage Transfer Station is located at

On the west side of the Tongziyuan Bridge in Jiulong Park, Economic Development Zone,

Covering an area of more than 17,000 square meters,

It adopts the most advanced in China

equipment and waste treatment technology,

The daily waste processing capacity can reach 450 tons.

The construction of Wanzhou Harrier Rock Garbage Transfer Station is progressing smoothly

The project will serve after completion

万州经开区、双河口、龙都、

Archway, five bridges, Bai'an Dam, Chenjiaba, peak,

Jiuchi and other streets and surrounding towns and townships

garbage transit transportation,

Become a service in the northeast area of Chongqing, garbage classification, compression and transfer,

Leachate treatment and bulky garbage crushing as a whole

Comprehensive demonstration of classified garbage compression and transfer station.

The construction of Wanzhou Harrier Rock Garbage Transfer Station is progressing smoothly

Restricted by the terrain,

The transfer stations are distributed in a stepped manner,

Anti-slide piles as an important part of the project,

Anchors, frame lattice beams, net spraying, etc

The slope support has been fully completed,

The two main factories are being reinforced.

Prepare for the next step of pouring.

Workers are installing drainage pipes,

Several large machinery and equipment are being leveled and backfilled.

The construction of Wanzhou Harrier Rock Garbage Transfer Station is progressing smoothly

According to the person in charge of on-site construction,

Construction is underway

The main plant of Harrier Rock Garbage Transfer Station,

60% of the main body has been completed,

Preparing to cap in June this year,

The whole project has completed 70% of the investment,

It is expected to be delivered in March 2025.

Reporter Tang Xiaohong