laitimes

Keep the original heart with ingenuity, see the sincerity with the ordinary - remember Xu Tao, the second water source project in Linyi City

author:Qilu one point

Qilu Evening News Qilu One-Point Reporter Gong Xucheng Correspondent Li Bingqiang

【Editor's Note】The opening of the second water source project in Linyi City marks that the water supply in the downtown area of our city has officially entered the era of "double water source". How did this project with high design standards, large project span and large number of beneficiaries be completed in less than a year and a half? Behind the project, how did the pragmatic and hard-working "Yimeng Water Steward" water steward overcome one problem after another, such as epidemic prevention and control, super heavy rainfall once in a century, and extremely cold weather? From now on, Qilu Evening News Qilu One Point walked into the frontline of the grassroots, discovered the story, listened to the story, and launched a series of reports on the construction of the second water source project in Linyi City.

Lying in the land of 10,000 acres of pear blossoms, the peaks are stacked with greenery, the Xujiaya Reservoir in Fei County, one of the eight major reservoirs in Shandong Province, is like a green pearl embedded in it, the blue waves are quiet, the level is like a mirror, here is the water source of the second water source project in Linyi City. The high-quality water source of Xujiaya Reservoir, through the relay ductile iron pipe, through the mountain, into the water, across the bridge, along the Wenliang River, Fei County's New South Outer Ring Road, the right bank of the Riverside Road, all the way "mighty", flowing into the Linyi City Second Water Source Project Water Purification Plant...

Keep the original heart with ingenuity, see the sincerity with the ordinary - remember Xu Tao, the second water source project in Linyi City

With water supply experience

Become the "leader" of the water transmission project

What the people want, what the government wants. In order to further improve the water supply guarantee capacity of Linyi Urban Area and meet the future development needs of the city, in 2019, the Municipal Party Committee and the Municipal Government were far-sighted, far-sighted and scientifically decided to start the construction of the second water source project in Linyi City, with Linyi Water Affairs Group as the main body of the project, specifically responsible for investment, construction, management and operation.

After nearly a year and a half, at 8:58 on June 27 this year, after more than two months of centralized commissioning, the second water source in Linyi City was officially opened to water. At that moment, staring at the continuous flow of raw water into the pressure distribution well, Xu Tao, the person in charge of the second water source project in Linyi City and a member of the Communist Party of China, was completely relieved, and a stone in his heart finally landed.

Keep the original heart with ingenuity, see the sincerity with the ordinary - remember Xu Tao, the second water source project in Linyi City

Xu Tao said that as the first provincial-level key people's livelihood project undertaken by the water affairs group, the Linyi City Second Water Source Project attaches great importance to and conscientiously deploys the project from the project feasibility study and environmental impact assessment to the project establishment and construction, and allocates all the backbone forces and concentrates superior resources into the project construction. Naturally, Xu Tao, who has 20 years of experience in water supply, was not only selected, but also appointed as a "leader", leading dozens of colleagues to plunge into the construction of water transmission projects at the beginning of construction.

"Time is tight and the task is heavy. At that time, I likened this project to a 'tough battle', when the battle started, I had to charge, I had to fight with a real gun, and if I chose to retreat, I really became a 'deserter'. Everything was difficult at the beginning, the burden was pressed on his body, Xu Tao checked the information, ran the construction site, asked the teacher, listened to the lectures, and was stunned from an ordinary manager to an "insider" in the construction of the project.

Keep the original heart with ingenuity, see the sincerity with the ordinary - remember Xu Tao, the second water source project in Linyi City

Adopt innovative technologies

Nibble down this "hard bone"

In the Spring Festival of 2020, shortly after the start of the water transmission project, the new crown pneumonia epidemic quietly swept in, facing the extension of the holiday, the suspension of the construction site, and the delay in the resumption of work, Xu Tao looked in the eyes, anxious in his heart, and grew a mouthful of burning bubbles. At that time, in order to resume work as soon as possible, Xu Tao wore a mask and packed lunch, ran the department unit from morning to night, handled the resumption of work procedures, and contacted the construction team to enter the site. The effort paid off, and while other construction sites were still in a state of shutdown, the water transmission project was already in full swing.

Keep the original heart with ingenuity, see the sincerity with the ordinary - remember Xu Tao, the second water source project in Linyi City

"The total length of the water transmission project is 32.4 kilometers, of which the tunnel part is 3.42 kilometers long, passing through more than 40 villages, the front line is particularly long, the terrain is also complex, not only over the mountains, but also through the river to dig the ground, the construction period left during the epidemic must find a way to make up for it." On June 24, 2020, Xu Tao squatted on the construction site and said while optimizing the construction plan with the construction party.

Keep the original heart with ingenuity, see the sincerity with the ordinary - remember Xu Tao, the second water source project in Linyi City

Due to the long depth of the cave, the small section, the difficulty of ventilation and smoke exhaust, the construction production and safety management of the two tunnels in the water transmission project are extremely difficult and risky, and the excavation progress is only 7 meters per day, which can be listed as a full-line control project. In order to catch up with the established construction progress and gnaw down this "hard bone" as soon as possible, Xu Tao led the staff to analyze the construction drawings with the participating units over and over again, discussed the construction plan again and again, and analyzed that through the innovative use of branch holes and two-way excavation technology, 2 branch holes and 6 working surfaces were added, and the construction period could be saved by 1/3.

Whether it is day or night, as long as the project is needed, Xu Tao must appear at the construction site for the first time. On July 23, 2020, Linyi ushered in heavy rainfall, and for a time the tunnel was completely flooded with water, and the pump pumped for 4 days before the construction of the cave could continue. Faced with the delay in the construction period, Xu Tao was so anxious that he could not eat and could not sleep. Even at 12 o'clock in the middle of the night, as long as he heard the sound of rain outside, Xu Tao could not help but put on his clothes and drive to the construction site to see. During the Mid-Autumn Festival, I wanted to have a reunion festival for a family of three, Xu Tao's front foot just entered the door, the meal was just put on the table, but the mobile phone rang. With a sentence of "coming soon", Xu Tao guiltily told his wife and children, "The tunnel on the construction site has just been blasted, and there is a bit of a problem with the surrounding rock situation, and everyone is waiting for me to discuss the plan together." After saying this, he turned around and went out the door, leaving only a shadow on his family.'s

Keep the original heart with ingenuity, see the sincerity with the ordinary - remember Xu Tao, the second water source project in Linyi City

Lead the construction staff

Run out of the "new speed of water"

The continuous high intensity of worry, hard work, and busyness, visible to the naked eye, is the white hair produced by Xu Tao's sideburns. "As soon as I woke up in the morning, I began to schedule the work schedule in my heart, and I lay in bed at night, unconsciously combing through the various links and problems during the day in my mind, and dreaming was a matter on the construction site." Xu Tao said that he poured too much effort into the water transmission project, just like he worked hard to feed his own children, and carefully cared for it to be slowly built.

In order to make the project completed on time, Xu Tao, who has been staying at the construction site, insists on non-stop people during the day, smooth communication at night, and people and cars running at any time. Many colleagues said that in more than a year, Xu Tao's phone was the most difficult to call, because he was always on the phone; some colleagues had jokingly taken his mobile phone to count, and in just half a day, his communication records had as many as hundreds...

Heaven rewards diligence, hard work is not deceived. In the face of extraordinary "time" and extraordinary "difficulty", Xu Tao firmly believes that as long as he is the first to do his work and his ambition is the first, there is no difficulty that cannot be overcome. For more than 400 days and nights, Xu Tao led all the construction personnel to implement the work measures of node target assessment and strengthen the implementation of the work in accordance with the work requirements of "inverting the construction period, wall chart operation, refining the target, and compacting responsibility", and tried all means to concentrate all forces, carefully organized and scientifically managed, optimized and optimized the construction plan, accelerated the construction speed and accelerated it, and did a "new responsibility for water affairs" and ran out of "new speed of water affairs"!

Keep the original heart with ingenuity, see the sincerity with the ordinary - remember Xu Tao, the second water source project in Linyi City

Wearing the stars and wearing the moon, facing the wind and rain, and "building dreams" with ingenuity... Under the leadership of Xu Tao, through the joint efforts of all the participants in the construction, at the end of last year, the main project of the linyi city second water source project was completed; in mid-April, the water transmission project and the water purification plant began to open the water commissioning section by section to further consolidate and improve the problems found; on June 27, the linyi city second water source project was completed and officially opened under the witness of the people of the city!

A generation has a generation's mission, and a generation has a generation's responsibility. Xu Tao, a member of the Communist Party of China who works hard, works hard and forges ahead, and dedicates himself selflessly, is only a microcosm of all fronts of water affairs. Stars do not ask the rushers, time does not pay off, standing in the new era today, Linyi water workers have accumulated full enthusiasm for work, focusing on "real", settling on "dry", holding their heads high, proud and passionate, striding on the road of high-quality development, ensuring water supply, promoting development, writing a new chapter, casting brilliance!