The first-time hot slip test was successful!

author:Shenzhen transportation

For xian fan who lives in Nanshan and Bao'an, line 1 and 11 are crowded every day. A commute time of 1 hour is a winner in life. However, it is expected that after the trial operation of this subway line within this year, it will be more convenient for friends to travel to work.

It is the subway line 12 known as the "Purple Xia Fairy". Recently, Line 12 has made new progress! Recently, Metro Line 12 first adjustment section hot slip test round! full! finish! Yes!

The first-time hot slip test was successful!

This marks the official launch of the joint commissioning of the equipment system with driving scheduling as the main line of the whole line, laying a solid foundation for the line to achieve the goal of high-quality opening and trial operation within the year.

The first-time hot slip test was successful!

The hot slip test of the first tuning section was successfully completed

Presumably, many old fans know that the first start of each subway line train after it is electrified should be dedicated to "hot slip", rather than the day when the passengers are officially operated.

What is "hot slip"?

The first-time hot slip test was successful!

In the hot slip test of the first adjustment section, the subway train departed from the Airport East Depot of Line 12 and traveled along the exit section to Shangchuan Station, ending at Huangtian Station, a one-way 10.9 km.

Through the hot slip test, the power supply, catenary, track, equipment and other systems are inspected, and the vehicle flow collection and pantograph network relationship are analyzed.

In order to fully carry out the hot slip test, the train will run back and forth from the left and right lines at low speed (not more than 20 km / h), medium speed (not more than 40 km / h), and high speed (60-80 km / h), respectively, with a total mileage of about 65 km and a maximum operating speed of 80 km / h.

The first-time hot slip test was successful!

A total of working groups such as safety supervision, joint dispatch room, technical support, commissioning and cooperation have been set up in this hot slide, and the close cooperation between each group and the division of labor are clear-

  • Technical and commissioning team: confirm the hot slip conditions in advance, and confirm 13 main control conditions and 6 basic conditions to ensure the stability of driving power supply and road safety.
  • Communication support group: The installation and commissioning of the 800M dedicated wireless system was completed 20 days in advance to ensure smooth hot-slip communication.
  • Safety Supervision Group: Strictly check the safety and boundary restrictions of the first adjustment section and the closure of the rail area, prevent personnel from entering the rail area during the hot sliding period, and ensure the personal safety of the participants.

The backbone of rail transit supporting the development axis of Shenzhen's western region

Metro Line 12 starts from Zuopaotai Station in Nanshan District and ends at Haitianyuan East Station in Bao'an District, with a total length of about 40.56 kilometers, the whole line adopts underground laying method, and There are 33 stations on the whole line of Line 12, of which 18 are interchange stations, which is the backbone of rail transit supporting the development axis of Shenzhen's western region.

The first-time hot slip test was successful!

From south to north, it connects Shekou Free Trade Zone, Nanshan Central Area, Bao'an Central Area, Xixiang Area, Airport East Area, Fuyong Area, Large Airport Area and Convention and Exhibition Area.

The first-time hot slip test was successful!

▲Schematic map of Metro Line 12 (station name is subject to actual completion)

At present, all stations on the line are fully capped, tunnels are all penetrated, and station decoration and auxiliary structure construction are actively advancing.

According to the plan, Metro Line 12 will be opened for trial operation within the year, at which time, the public transportation structure in nanshan central area and Bao'an central area will be greatly optimized, the travel environment of citizens will be improved, the increasing traffic pressure will be alleviated, and the quality of Shenzhen will be effectively improved.