The purchase of a set of apartments in Xi'an "SPRING+ Timao" has been postponed for half a year and still cannot be delivered

author:Xi'an Business Network

In the face of repeated delays in delivery, Ms. Yu's heart became more and more bottomless.

In January 2019, through the introduction of the housing agency, Ms. Yu purchased an apartment located in "SPRING + Timao" on Eurasia Road in Xi'an City, with an area of more than 30 square meters, a total price of more than 450,000 yuan, and a down payment of more than 210,000 yuan. Ms. Yu said that according to the "Contract for the Sale and Purchase of Commercial Housing" signed with the developer, the house should be delivered before August 30, 2021, but there was more than one delay, "On August 30 last year, the developer sent us a letter saying that it was affected by the epidemic and the house should be postponed to January 20, 2022. Ms. Yu said that on January 20 this year, due to the epidemic in Xi'an and other reasons, the house has not been delivered.

The purchase of a set of apartments in Xi'an "SPRING+ Timao" has been postponed for half a year and still cannot be delivered

The reporter saw in the "Contract for the Sale and Purchase of Commercial Housing in Xi'an City" provided by Ms. Yu that the delivery time and procedures stipulated that "the seller shall deliver the commercial housing to the buyer before August 30, 2021".

On August 23, 2021, the developer Xi'an Chanba Ecological District Spuri Real Estate Co., Ltd. issued the "Notice of Delayed Delivery of spring Timao Project" to the owner, saying that "due to insufficient understanding of the construction progress affected by epidemic prevention and control and other reasons, although the construction has been actively organized to catch up with the progress, but still caused the project delivery delay, our company apologizes, and the company will pay compensation to the owner in accordance with the contract... The delivery of the house is tentatively scheduled for you on 20 January 2022, subject to the notice of delivery issued. The reporter dialed the contact information left below the notice, but no one answered.

"The building was topped out in April last year, but according to my observation, there has not been much progress so far." Ms. Yu said that it has been more than half a year, but when it will be delivered is still unknown.

The purchase of a set of apartments in Xi'an "SPRING+ Timao" has been postponed for half a year and still cannot be delivered

The reporter noted that some citizens have worried about the late delivery of the building through the people's network leadership message board to reflect, on December 6 last year, Xi'an Chanba Ecological Management Committee had replied that the project is the Spuri Square smart maker center project, in April 2021 the main structure has been capped, but the follow-up construction progress is slow, there is a delay in delivery. In response to the problem of housing delivery, the staff of the Housing and Construction Bureau of our committee has interviewed the developer many times in the early stage, held a coordination meeting, urged them to take multiple measures at the same time, and raised construction funds from all aspects to ensure the follow-up construction of the project. On April 1, 2021, the Measures for the Supervision and Administration of Pre-sale Funds for Commercial Housing in Xi'an City came into effect, and the administrative departments in charge of housing construction in each district and county and the management committee of the development zone are responsible for the supervision and management of the deposit, expenditure and use of pre-sale funds for commercial housing development projects in their jurisdictions. According to the pre-April 1 policy, the supervising bank is responsible for the daily supervision of the receipt, deposit and use of pre-sale funds for regulatory projects that have signed the agreement. At present, developers are actively working to raise funds for project construction from the aspects of sales of buildings and bank loans. The Housing and Urban-Rural Development Bureau will also continue to pay attention to and urge developers to speed up the financing and construction progress, and strive to complete the construction as soon as possible and meet the delivery conditions.

On February 9, the reporter called the marketing hotline of Xi'an Chanba Ecological District Sprite Real Estate Co., Ltd., and the staff said that the delivery was delayed due to the impact of the epidemic, because it had just resumed work, a detailed plan was being formulated, and the plan would be formulated in these two days, and a letter would be sent to the owner at that time.

On the morning of February 10, the staff of Xi'an Chanba Ecological Zone Spuri Real Estate Co., Ltd. replied to reporters, the other party said that the postponement of the delivery of the house is affected by objective factors such as the epidemic, the project is currently in the final stage, and the workers will return one after another around the fifteenth of the month. On February 14, under the auspices of the staff of the government department, the owner's representative will be invited to negotiate and give the owner an accurate delivery time and specific plan.

Source: Two Or Three Mile Information