Demolition for many years only built two buildings! When will the villagers in Laiwu be able to move back?

author:Lay buy a house

1

Hello leader, Laiwu District Pengquan Street Office North Xiaoyi Village demolition project has been carried out for many years, only two buildings built alone, no other progress, the whole village of more than 2,000 mouths of more than 700 households are now scattered throughout the rent, rental costs by the village collective to pay, now the annual rental cost of tens of millions, my village for many years accumulated collective assets wasted here. It is hoped that the government will coordinate the restart of this project to protect collective assets from waste, and the villagers will return to their homes as soon as possible.

Hello! The question you reflected, Laiwu District Pengquan Street Office conducted a survey, and now the reply is as follows:

In 2018, Beixiaoyi Village began to survey and evaluate, started the renovation of the old village, signed a resettlement agreement in December, began demolition in January 2019, and demolished all buildings in one year. A total of 16 buildings were built and resettlement in Beixiaoyi Village, and the procedures for the first two buildings 1 and 6 were completed and the main body was completed; the procedures for the five buildings of No. 7, No. 10, No. 11, No. 12 and No. 13 were completed, and construction had begun to more than one floor; the construction procedures of the remaining 9 buildings were being actively handled. On the issue of lease fees, the North Xiaoyi Village Committee has negotiated with the developer before that, and the developer is responsible for the lease fee for two years. Pengquan Street will further urge Beixiaoyi Village to continue to accelerate the development of relevant work, and jointly promote the construction of relocation houses in Beixiaoyi Village, so that villagers can move back as soon as possible.

2

Laiwu District Fengcheng Street LvHuayuan Community Women's And Children's Hospital Home Community, the heating side is Hongjing Property. However, the indoor temperature has always been 15 ° C, which obviously feels cold. At the same time, in order to save costs, enterprises turn off the heating valve without authorization after three o'clock in the morning. Investigate and hold accountable.

Hello! The problem you reflected, Laiwu District attaches great importance to, immediately transferred to the Laiwu District Fengcheng Street Office for handling, and now reply as follows:

After verification, the home of the maternity and child care hospital is the dormitory building of the maternal and child health hospital, which was originally a unit management community. In 2021, in accordance with the principle of territorial management, it is handed over to the community management, and now Hongjing Property is responsible for the heating method, and the heating method is secondary heating for the flow of the property purchase heating enterprise.

There are 110 households in the women's and child care hospital community, and some residents have not paid the heating fee, and the property needs to reasonably arrange the flow to ensure the normal operation of the entire heating period. And the community belongs to the old community, the thermal insulation is poor, which affects the heating effect.

In the next step, the community will actively supervise the property, reasonably arrange the flow of traffic, and ensure that the heating effect during the heating period meets the standard. At the same time, the women's and child care home community is currently preparing to establish a owners' committee, and the community will actively assist the owners of the community to complete the establishment of the owners' committee as soon as possible to realize the owner's independent management.

I wish you a happy life!