The construction of the Lexi Expressway Daliangshan No. 1 Tunnel has entered the fast lane After the completion of the whole line, liangshan Zhaojue to Meigu only takes 4 hours

author:Cover News

Cover news reporter Cao Fei

On January 22, the Daliangshan No. 1 Tunnel, the Lexi High-speed Control Project of Shudao Group, came from the new progress: the parallel guide hole and the inclined shaft of the tunnel were smoothly connected and penetrated, marking the successful completion of the first phase of the overall project of the tunnel.

The construction of the Lexi Expressway Daliangshan No. 1 Tunnel has entered the fast lane After the completion of the whole line, liangshan Zhaojue to Meigu only takes 4 hours

The Lexi Expressway Daliangshan No. 1 Tunnel is the longest expressway tunnel in the southwest region of mainland China and the first expressway tunnel in Mainland China to use TBM auxiliary construction.

The tunnel has a total length of 15.3 kilometers, close to the Dafengding National Nature Reserve, Sichuan Province Mamize Nature Reserve and other giant panda habitat protection areas, in order to protect the natural environment and accelerate the construction progress, Lexi Company adopts the combination of TBM flat guide + main hole drilling and blasting method, filling the gap of domestic highways using TBM construction technology to assist tunnel construction.

The construction of the Lexi Expressway Daliangshan No. 1 Tunnel has entered the fast lane After the completion of the whole line, liangshan Zhaojue to Meigu only takes 4 hours

Affected by the inconvenience of transportation in Liangshan Prefecture and the objective factors of frequent natural disasters in the rainy season, the TBM equipment entered the site 3 months later than the original time, and all the participants of the Lexi Expressway overcame the transportation difficulties and complex geological conditions such as tunnel fault fracture zone, gas, surge water, and surrounding rock deformation, and ensured the continuous, balanced and rapid excavation of TBM. After 13 months of hard work, the task of penetrating the first phase of the flat guide and inclined shaft of the Daliangshan No. 1 Tunnel was completed 77 days ahead of schedule.

At the same time, during the construction of the excavation, the "Yuecheng Liangshan" TBM set a record for the fastest daily advance of 49.12 meters and 730.2 meters per month for the TBM of the mainland expressway.

After the flat guide tunnel of Daliangshan No. 1 Tunnel and the inclined shaft are penetrated, the inclined shaft will assist the construction of the main tunnel of the Daliangshan No. 1 Tunnel, undertake more tasks of construction, transportation and personnel safety, and the tunnel construction will enter the accelerated fast lane.

The construction of the Lexi Expressway Daliangshan No. 1 Tunnel has entered the fast lane After the completion of the whole line, liangshan Zhaojue to Meigu only takes 4 hours

Up to now, the Pingyin Cave of the Daliangshan No. 1 Tunnel has completed a total of 7856 meters, and it is expected to achieve the breakthrough of the Pingdao Cave in January 2023, the excavation support of the left line of the exit has been completed by 2116 meters, and the excavation support of the right line has been completed by 3298 meters, and the overall breakthrough of the main hole is expected to be achieved in May 2024.

Lexi Expressway is the mainland's first deep into the hinterland of Sichuan Liangshan, is the Sichuan Liangshan 2 million Generations of expectations, after the full completion and opening of traffic, will be connected with Chengdu- Chongqing, Beijing-Kunming, Rongli and other national highway trunk lines, not only completely end the history of Liangshan Prefecture Zhaojue, Meigu and Lei Bo three counties without highways, at the same time to Chengdu driving time from the current 10 hours to 4 hours, to consolidate and expand the Liangshan Prefecture poverty alleviation results, It plays a very important role in helping rural revitalization and foreign cultural exchanges and integration, and realizing the common prosperity of people of all ethnic groups.