Nearby construction site construction, residential buildings appear fist-sized cracks? In the face of doubts, the construction party did not come forward

Mr. Li, who lives in Hengyu Village, Fuzhou, said that in early October, construction began at the construction site, which was only one road away from his home, and when he drove the pile, his home was like an earthquake. What worries him even more is that there have been different degrees of cracking in his home and neighbors' homes recently.

The construction site is next to private houses

Residents: The house is now cracked after many days of construction

Nearby construction site construction, residential buildings appear fist-sized cracks? In the face of doubts, the construction party did not come forward

Mr. Lee

The steps and main beams of the house were cracked, and the construction site moved a little, and the whole of our side bulged.

Not only at Mr. Li's house, the reporter also saw many cracks in his neighbor's house. Other villagers said the main beam of his house was also damaged.

Nearby construction site construction, residential buildings appear fist-sized cracks? In the face of doubts, the construction party did not come forward
Nearby construction site construction, residential buildings appear fist-sized cracks? In the face of doubts, the construction party did not come forward
Nearby construction site construction, residential buildings appear fist-sized cracks? In the face of doubts, the construction party did not come forward

Villagers agree that the cause of the crack is the construction site that is only one road away from their house.

Nearby construction site construction, residential buildings appear fist-sized cracks? In the face of doubts, the construction party did not come forward

Villagers told reporters that after the cracks appeared, the construction party also came to the scene to mark, but there was no follow-up after that. This makes residents very worried, so close to the construction site, this will continue to affect the residence.

Nearby construction site construction, residential buildings appear fist-sized cracks? In the face of doubts, the construction party did not come forward

At the scene, it can be seen that cracks of varying degrees have indeed appeared in the homes of several villagers. However, based on naked eye observation alone, it is not possible to judge how long these cracks have been cracked, nor can it be concluded that these cracks are related to the construction of the nearby project.

Village Party Secretary: The construction party has carried out safety monitoring

In the near future, multi-party communication will be organized

In order to further verify the cause of the crack, under the leadership of villager Mr. Li and others, the reporter also came to one of the construction units called Fujian Sijian Group, but the person in charge was not there that day.

Subsequently, the reporter also came to the Hengyu Village Committee to further understand the situation. The village branch secretary told reporters that at present, there are actually two construction units around the villagers' houses, one is a resettlement housing project, the other is a commercial housing project, since receiving feedback from the villagers, they have also taken the lead in convening the local street office, two construction units and villagers to jointly negotiate and solve, and also invited a third-party appraisal agency.

Nearby construction site construction, residential buildings appear fist-sized cracks? In the face of doubts, the construction party did not come forward

The village party secretary said that the monitoring results have not yet been released, so the next step of the plan has not yet been carried out. On the spot, the village party secretary of Hengyu Village also helped contact the telephone number of a person in charge of the construction party of the resettlement housing project.

Nearby construction site construction, residential buildings appear fist-sized cracks? In the face of doubts, the construction party did not come forward

After the other party learned that the reporter intervened, he hurriedly introduced a few words and hung up.

At the scene, the villagers pointed out that because the second monitoring time did not know when, they were worried that the construction during this period would have a greater impact on the house, so they hoped that the relevant second monitoring could be carried out as soon as possible.

The reporter returned to visit the construction unit

Recently, the reporter came to Hengyu Village again and found a staff member of the commercial housing project, who said that when there was a crack in the nearby resident's home, they did not carry out construction, in view of the current situation, it is necessary to wait for the identification results of the third party to negotiate how to solve it. Subsequently, the reporter once again found the construction unit of the resettlement house - Fujian Sijian Group. But the staff said one moment that the manager was on the way to come, and the next moment he said that he was on a business trip.

Nearby construction site construction, residential buildings appear fist-sized cracks? In the face of doubts, the construction party did not come forward

Subsequently, the reporter also came to the street of the district, and unfortunately, the staff in charge of the matter went out. The villagers also hope that the street can take the lead in organizing a coordination meeting between the villagers' representatives and the construction party to promote the settlement of this matter.

Nearby construction site construction, residential buildings appear fist-sized cracks? In the face of doubts, the construction party did not come forward

Subdistrict Office: The tripartite coordination meeting will be organized as soon as possible

Before the deadline, the person in charge of the street called the reporter, saying that they were working on the matter, and replied to the villagers' concerns, and would ask a professional third-party agency to conduct an appraisal a month after the construction party had finished piling.

Secretary Xie of the Party Working Committee of the District Subdistrict

Next, because the pile has not been finished, the designated person in the village will go to each household every day to inspect and make records, is there any change, in the end, has the safety of this house been damaged? The second is to make a good report, in case any household affects the safety of the house because of piling, we will mobilize the villagers and force the villagers to move out. After the pile is finished, we will call a third-party appraisal, a special appraisal agency, to make an accurate appraisal of the damaged house, and we will call them to take responsibility for the claim, the claim of the claim. Reporter: So when will the second monitoring start? About a month later, a month after the pile is laid? Reporter: Can the street help coordinate it, such as the three parties, resident representatives, and construction parties to hold a coordination meeting together to see what has been caused by this impact, how to promote this matter next, how to solve it? Like this piece involves several departments, I go back to the report, after the report, to formulate a coordination meeting plan, after the report to hold a coordination meeting, and then some of the process to inform the villagers.

The construction site next to the residential building is bound to affect the lives of residents, and I once again hope that Fujian Sijian Group can come up with its due attitude and properly handle this matter. Regarding the progress of this matter, the gang will continue to pay attention.