just! Qingdao Metro Line 4 ushered in important progress, further from the opening of 2022

Recently, Qingdao Metro Line 4 has been in constant motion

The first cover dug station was successfully capped

Bidding for the construction of decoration and renovation works in public areas

……

Qingdao Metro Line 4 ushered in a wave of construction progress

A few days ago, the Jinsong 7th Road Station of Qingdao Metro Line 4, which is managed by China Railway Construction Investment Group and undertaken by China Railway 25th Bureau Group, was successfully capped. The station is the 20th-roofed station on the line and the first station on Line 4 to be capped by the cover digging method.

Jinsong 7th Road Station is located at the intersection of Liaoyang East Road and Jinsong 7th Road and is the 14th station on the line. The total length of the station is 472.6 meters, the width is 22.9 meters, the depth is 18 to 26 meters, and there are 11 entrances and exits and 4 sets of wind pavilions.

just! Qingdao Metro Line 4 ushered in important progress, further from the opening of 2022

In addition, on October 11, it was learned from relevant channels that the construction bidding announcement for the decoration and decoration project of the public area of Qingdao Metro Line 4 was released, and the construction progress of Line 4 entered the final stage, laying a solid foundation for the early opening and operation.

just! Qingdao Metro Line 4 ushered in important progress, further from the opening of 2022

Basic information about the project

1. Project Overview: Qingdao Metro Line 4 Engineering Line starts from Renmin Hall Station and ends at Dahedong Station, with a total length of about 30.718km, a total of 25 stations, 1 control center, 1 depot and 1 comprehensive base.

2. Bidding content: Qingdao Metro Line 4 platform, station hall, entrance and exit passage (excluding the People's Hall Station) construction drawings to deepen the design and decoration project, public artworks and other production, installation and after-sales service. For details, please refer to the bill of quantities and the user requirements.

3. The project is divided into six lots

There are 3 sections of one bid: Qingdao University Affiliated Hospital, Guanxiang Mountain (Municipal Hospital), Taishan Road

3 second bidding sections: Changle Road, Inner Mongolia Road, Haibo Bridge (Haici Medical)

There are 3 three lots: Anshan Road, Wrong Port Ridge, and Fuliao Interchange

There are 5 sections of the four bids: Women's and Children's Hospital, Jinsong 3rd Road, Jinsong 4th Road, Jinsong 7th Road, Liaoyang East Road

There are 7 five-bid sections: Dongjiaxiazhuang, Keyuan Jingqi Road, Zhangcun, Pengjiazhuang, Nanzhaike, Xiaolaoshan, Shazikou

There are 3 six bidding sections: Duanjiabu (Laoshan No. 6 Middle School), Dengying, Dahedong

just! Qingdao Metro Line 4 ushered in important progress, further from the opening of 2022

On the afternoon of September 23

Zhang Jiangang, Secretary of the Party Committee and Chairman of Qingdao Metro Group

Guest "Minsheng Online"

Around the theme of "rail transit construction and operation in our city"

There was an online exchange with netizens

just! Qingdao Metro Line 4 ushered in important progress, further from the opening of 2022

Among them, Zhang Jiangang introduced it in the online conversation

About the latest construction progress of Line 4:

"The civil works of Metro Line 4 will be completed at the end of the year

Other words

As soon as the end of next year

You can take line 4

How important is Line 4 for everyone's travel?

Let's put it this way

It's actually a true "east-west artery."

Passing through the old town of the south of the city, the back of the fushan mountain in the north of the city, the Laoshan Scenic Area and so on

After the opening, the main urban area will be realized

Five lines are operated in a network

Line 4 "Connected to the Grid"

Let the travel and transfer of the old convenient ~

Good news about the new line

More and more

The day it opened

It has also entered the countdown state

Let's go next

Together with great anticipation

Welcome to Line 4!

Read on