Huangshi Daily News (reporter Wang Tao) On the morning of the 10th, Rao Peng was busy with his family to carry his family's belongings to the trailer, and beads of sweat flowed down his cheeks, but his heart was happy.
"Finally moved!" Rao Peng is a demolition household in the temple community in Xialu District, and although he is a little reluctant to face the relocation, he is full of yearning for his future life: "Changing the environment, the air is better, which is good for the health of children and families." "Like Rao Peng, the temple tablets were the first 52 households to vacate. The reporter saw at the scene that most residents have emptied their homes, and only some debris remains in the house.
Lu Chuilong, director of the General Headquarters Office of the Environmental Remediation Work of the Temple Tablets in Xialu District, introduced that because the temple tablets are relatively close to enterprises such as Daye Nonferrous metals and emerging pipe industries, residents suffer from air, dust, noise and other environmental impacts, and this problem has also been included in the key issues assigned by the Central Ecological environmental protection inspector. In order to completely solve this environmental problem, the Lower Lu District decided to start environmental remediation work on the Temple Pass area. The environmental remediation work involved the relocation of 244 houses.
Lu Said that since the start of the demolition work on June 16, 227 households have signed contracts, with a signing rate of 93%.

Xialu District Temple Area Environmental Remediation Project Xinjie Office Plot House Demolition Project:
First, the basic situation of the project
1. Project number: HBBY-2021029
2. Project Name: Environmental Remediation Project of Temple Area, Xialu District, Xinjie Office, House Demolition Project
3. Procurement method: competitive consultation
4. Government procurement budget: 1.5 million yuan
4. Maximum price: 30 yuan / square meter
5. Procurement demand: About 50,000 square meters of house demolition, garbage removal and site leveling of the new street office plot.
6. Contract performance period (duration): completed within 60 calendar days.
7. Quality requirements: All buildings and ground appurtenances in the area to be demolished are demolished; all garbage is cleaned up and the site is leveled. At the time of acceptance, the natural ground elevation is flat, there is no accumulation of debris, and the foundation is cleaned up as qualified.
8. This project does not accept consortiums.