Since the beginning of this year, Funing County has adhered to the new development concept to lead high-quality development, with a high degree of concentration on the stock, adjust the structure, promote development, while promoting the landing and production of new enterprises, the existing enterprises will be cultivated and strengthened, to ensure that funing county's industrial economy to achieve high-quality development.

On July 6, the reporter was in the workshop of Huaining Energy Technology, only to see that the project construction personnel were distributed in different areas in a tense and orderly manner, a fiery scene of big and fast. It is understood that Jiangsu Huaining Energy Technology Project is divided into three phases, the first phase of the plan total investment of 800 million yuan, the new two photovoltaic module production lines, the current entire workshop of a production line has been installed, the other production line is also in the process of preparing for installation in chronological progress.

"Since the full line of water and electricity was completed in mid-to-late June, we have entered the equipment installation and commissioning link, and we will complete the installation and commissioning of the equipment as soon as possible." Shen Min, chief operating officer of Jiangsu Huaining Energy Technology Co., Ltd., said, "We are currently catching up with the progress of the facility, and after all the equipment is installed and debugged, the company can carry out trial production." ”

Jiangsu Huaining Energy Technology Project is divided into three phases, the first phase is 800MW of high-efficiency modules and 200MW of green building materials project, signed on May 18 last year, with a planned total investment of 800 million yuan; the second phase is a 2GW heterojunction photovoltaic cell project with a planned total investment of 1.4 billion yuan; the third phase is a 1GW heterojunction photovoltaic cell and 1GW high-efficiency module project, with a planned total investment of 800 million yuan. The project is expected to be completed and put into operation in May 2022, with an annual output value of about 2.5 billion yuan and profits and taxes of 300 million yuan.

"The 2GW heterojunction photovoltaic cell project started on May 19 this year, the project uses 100 acres of existing land, builds a new plant of about 40,000 square meters, and plans to purchase more than 200 sets of equipment such as fleece machines, screen printing, PECVD, and cleaning machines." Shen Min said, "Our two production lines are currently the mainstream fully automatic component production lines in China, which can be compatible with the production of 210, 182 and 166 versions of the components. At present, we already have our own orders and OEM orders, waiting for the production line to be installed and debugged as soon as possible. ”

Project equipment installation is in full swing, enterprise production is also in full swing, July 6, the reporter saw in the production workshop of Jiangsu Huaen Wind Power Equipment Co., Ltd., the workers are skillfully grinding, welding steel plate and glue injection and other blade processing processes, technicians are on the two sets of 71.5 meters of mold parameter debugging and blade main molding and mold, the company is currently in hand production tasks are sufficient, the enterprise to achieve full load production.

"Now our company has sufficient orders in hand and is producing at full capacity." Zhang Zhengjun, general manager of Jiangsu Huaen Wind Power Equipment Co., Ltd., said, "Our company is mainly sold to Huayi Group in Zhejiang, this year's orders are about 60 sets, the total contract amount is about 120 million yuan, after signing the contract, the production plan is arranged until the end of this year, and we will increase manpower investment in the later period to ensure that the annual production plan is completed on schedule." ”

In addition, Hua'en Wind Power has also increased investment in technological transformation, introduced a number of new technical equipment, made great changes and improvements to the blade forming process and supporting tooling equipment, and continuously refreshed the wind power blade record in Funing County, laying a solid foundation for the company's high-quality development. "Our company upgraded the vacuum auxiliary material arrangement system, using the in-line infusion rubber machine and the in-line and molding machine, which ensures the precise control of the number of resin and compound adhesives used, reduces our production costs, and also improves the quality of the products." Zhang Zhengjun said, "In the next step, we will increase research and development efforts, continuously optimize the production process, improve product quality, and improve market competitiveness." ”

Up to now, the industrial enterprises in Funing County have achieved a total of 20.44 billion yuan of full-caliber invoice sales, an increase of 45.1% year-on-year, achieved full-caliber taxable invoice sales of 20.13 billion yuan, an increase of 45.9% year-on-year, and realized the tax of industrial enterprises into the warehouse of 830 million yuan, an increase of 49.8% year-on-year.