Text, photo/ Yangcheng Evening News all-media reporter Liang Zhengjie correspondent Pan Jinliang
Foshan Gaoming Hecheng Xi'an area infrastructure construction project is stepping up, including the expansion project of the northern section of Haitian Avenue, a total of 11 roads are about to usher in construction and upgrading, with a total investment of about 500 million yuan.
On Libei Road, which connects to the north of Haitian Avenue, workers are covering the roadbed with bare mud. The construction unit said that Libei Road has just completed the soft foundation treatment and high-pressure rotary pile spraying operation, and as the project accelerates, the next step will be to clear all the road surfaces under construction.

Liu Weiguang, on-site production manager of the infrastructure supporting construction (the first phase) in Xi'an area, said that the previous process has been completed, and the next step will be experimental testing, that is, in accordance with the government's environmental protection requirements, all bare soil is covered to meet the requirements of dust prevention.
The basic supporting construction project of Xi'an Area of Hecheng Street is designed and constructed in two phases, involving a total of 11 roads for construction and upgrading, the main construction contents include: road engineering, traffic engineering, rainwater engineering, sewage engineering, culvert engineering, pipeline protection culvert engineering, greening engineering, lighting engineering, etc., with a total investment of about 500 million yuan.
Liu Weiguang said that the first phase of the project involves the construction and upgrading of 5 roads, which have been cleared at present, and the site will be fully closed after completion.
According to the relevant person in charge of the Hecheng Street Engineering Construction Center, the two phases of the project began in March and June this year, at present, a road has been completed, 5 roads are under construction, and a number of roads are undergoing preparatory work, and construction has recently begun.
All along, the north and west side of Haitian Avenue road has not been able to start construction, the current use of the east side of the lane unilateral two-way traffic, the lane is relatively narrow, the expanded north section of Haitian Avenue will have 6 lanes, can achieve bilateral two-way traffic, effectively improve the road accessibility and smoothness.
Ou Guanshan, an engineer at the Hecheng Street Engineering Construction Center, said that the transformation of Haitian Avenue North is currently communicating with the planning department, and will continue the next step after the planning department issues a reply opinion.