Lintong Iron Furnace Street renovation has been delayed for one year Street Office: It has been restarted

Video loading...

Recently, some netizens posted "Lintong has an iron furnace street" in the China Business Forum, saying that the iron furnace street in front of their own door, the road surface has been dug up by the construction team for nearly a year, but the project has not made any progress, and the renovation project has not been completed so far. There are elementary schools and junior high schools next to this road, and it is difficult for children to travel to school due to road excavation, and it is usually inconvenient for the elderly to pass.

Lintong Iron Furnace Street renovation has been delayed for one year Street Office: It has been restarted

Huashang Network sent a letter to the Lintong District People's Government on this matter, and after an investigation by the Iron Furnace Street Office, it was found that the netizens reported that the situation was partially true. The start date of the Iron Furnace Street Market Town Project is July 20, 2020, and the various underground pipe networks in the early stage have been completed, and the remaining subgrade and pavement have not been completed. The reasons for the slower construction are mainly due to:

First, the underground pipeline of the difficulty of the project is complex, the boundary between the road boundary and the residential homestead is blurred, the amount of earthwork for replacement is large, and the construction period spans the rainy season and the busy agricultural season to bring greater difficulties to the participating parties.

Second, because the early construction is mainly the laying of the main network, the excavation depth of the earthmoving is deep, and the earthwork operation is greatly affected by the weather.

Third, because the project involves the burial of rainwater and sewage pipes (the rainwater pipes have been buried at present), the relocation of water pipes, the landing of network cables and road construction, the construction needs to dock with the district water bureau, the water supply station of the iron furnace market town, and the four major operators of mobile, Unicom, telecommunications, radio and television, which have a certain impact on the progress of the project.

Fourth, due to financial problems a few years later, the project was adjusted, and the current street office has actively docked with the Transportation Bureau, because the project adjustment needs to go through certain procedures, it is expected to start in full at the end of April, and the construction will be completed 3 months after the start of construction.

At present, the street office has been coordinated in place, and after the next rain, after the road surface is no longer wet, it will actively urge the construction unit to start and implement the next stage of road projects, ensure quality and quantity to catch up with the progress, and complete the construction as soon as possible.

On the afternoon of April 29, a reporter from Huashang Network received feedback from netizens that several excavators were under construction on the surface of Iron Furnace Street, and the renovation project had begun again.