At the construction site of the third phase of Kenmet (Guangde) Intelligent Manufacturing Industrial Park project in the Municipal Economic Development Zone, there are many tower cranes, and more than 400 construction personnel seize the "golden period" of construction, catch up with the schedule, compete for the construction period, and constantly refresh the "progress bar" of construction.
Project Manager: Zhixiang Tong
We are now carrying out masonry and secondary structure construction, and plan to complete the capping of the main structure and plant structure in mid to late August.
The Kenmet (Guangde) Intelligent Manufacturing Industrial Park project is constructed in two phases, and the first phase of the project is currently under construction. As the contractor, Guangde Economic Development Zone Investment and Development Group Co., Ltd. is stepping up its efforts to urge the construction unit to reverse the construction period, and solidly promote the construction progress according to the time node through measures such as refining the construction plan and scientifically scheduling resources.
Li Donghui, Deputy Director of the Engineering Department of the Municipal Economic Development Group
In the next step, we will require the construction unit to increase the investment of manpower and material resources, speed up the process conversion, and increase night construction. On the premise of ensuring safety and quality, we strive to complete and deliver by the end of December 2024.
It is understood that Kenmet (Guangde) Intelligent Manufacturing Industrial Park project is a key project in the province, which can achieve an annual output of 100,000 sets of medical, instrumental, semiconductor equipment and 80 million parts after completion and operation. The total investment is 2 billion yuan, the first phase of the investment is 1 billion yuan, covering an area of 120 acres, with a total construction area of 117,000 square meters, and it is expected that the output value of the first phase will be 750 million yuan after all the production is completed, and the annual tax payment will be 30 million yuan.
Source: Municipal Financial Media Center Reporter: Jiang Wen Intern: Xie Yunpei, Liu Ziqian, Zhang Ruiqi Editor: Wang Han, Yang Jing Review: Mei Miao