1. Machinery Fee
1.20cm thick concrete pavement breaking: 70 yuan per cubic meter, 0.2 cubic meters per square meter need to be broken, a total of 14 yuan/㎡. This part of the cost involves the use of heavy equipment such as crushers for pavement breaking operations.
2. Dump truck garbage transportation (tentative 10 kilometers): 1.2 yuan per kilometer, 10 kilometers per square meter, multiplied by a coefficient of 1.41, a total of 3.38 yuan / square meter. This part of the cost includes the cost of transporting the broken concrete waste to the designated location.
3. Disposal fee: 60 yuan per cubic meter, 0.2 cubic meters per square meter, a total of 12 yuan/㎡. This part of the cost refers to the cost of disposing of or disposing of waste concrete.
2. Management & Profit
1. Management + profit, etc.: accounting for 15% of the total cost, that is, 4.41 yuan/㎡. This part of the fee includes project management and operating costs, as well as the contractor's expected profit.
3. Taxes
1. Tax: 9% of the total cost, that is, 3.04 yuan/㎡. This part of the fee is calculated according to the local tax regulations.
Total cost
1. Total cost quotation: 36.83 yuan per square meter. This total cost covers everything from the use of machinery to the removal of waste, disposal, management and profits, and taxes.
Through the detailed cost breakdown above, the specific composition of each expense can be seen, which helps to more accurately evaluate and control project costs. In practice, these costs may be adjusted by region, market price fluctuations, project size, and other factors.