Jiang Hanfeng reported: In less than a year, the newly built Yanjiatai Gate of the Jingjiang River Embankment has completed 80% of the total project volume, and the gate has recently been opened to water, marking that the project has the basic function of flood control and irrigation.

Overlooking the Jingjiang River embankment, the Yangtze River water is flowing into the downstream channel through the gate of the new Yanjiatai Gate, and after nearly a week of water testing, the Yanjiatai Gate is generally running well.

Fully upgraded! The Yanjiatai Gate of the Jingjiang Embankment was opened to divert water

Lv Zhiqiang, the person in charge of Hubei Huaxia Water Conservancy and Hydropower Co., Ltd.: We carried out the opening of the gate on April 23 and the opening of the gate on April 30.

The original Laoyanjiatai gate was built in 1966, is a two-hole arch culvert structure, each hole is 3 meters wide, 3.5 meters high, the elevation of the gate floor is 30.5 meters (Wusong frozen), the design flow is 37.6m/s, and the irrigation farmland is 402,000 mu. At the end of 2020, the Hubei Provincial Department of Water Resources conducted a safety appraisal of the Yanjiatai Gate as a Class IV gate, and recommended that it be demolished and rebuilt.

In the entrance section of the newly built Yanjiatai Gate Project, bulldozers are repairing the bank slope, and workers are building the superstructure of the lock chamber. The main building level of the newly built Yanjiatai Gate is Class I, which is a 3-hole culvert gate with a single hole net size of 4.0x4.0 meters, a floor elevation of 28.40 meters, and a design flow of 41.6m/s. The total length of the box culvert is 76 meters, of which the sluice chamber section is 16 meters long and the embankment section is 60 meters long.

Fully upgraded! The Yanjiatai Gate of the Jingjiang Embankment was opened to divert water

Yanjiatai gate project officially started on November 15 last year, the planned construction period is one year, up to now, the main projects completed are the removal of the old culvert gate, the construction of the culvert gate foundation cast-in-place pile and the culvert gate cushion pouring, the gate chamber pouring and the gate installation project.

Lv Zhiqiang, the person in charge of the site of Hubei Huaxia Water Conservancy and Hydropower Co., Ltd.: We plan to repair the gate chamber in May, install the hoist in June, and carry out the automatic opening and closing of the gate, and carry out the construction and restoration of informatization after the flood season, which is planned to be completed in November this year.

After the reconstruction, the new communication network and information systems such as information security, video surveillance system, gate control system, application system and system integration will be built. After completion, the Yanjiatai Gate will better ensure flood control safety and improve irrigation efficiency.

Xue Min, deputy director of Jiangling Branch of Jingzhou Yangtze River Management Bureau: Our hoist has been upgraded from the original screw type to the hydraulic type, and we all rely on manual control on site, and now we can implement information-based remote control, and are equipped with professional monitoring facilities for flow, water level and water quality.

(Reporter: Tang Hua, Chen Xiaowu/Editor: Wang Xiangming/First Instance: Tang Jie/Second Instance: Wang Taofang/Third Instance: Jiang Min)

Jiang Hanfeng client, the first end of Jingzhou news. Pay attention to Jingzhou's government affairs, people's livelihood, and the big and small things around you, create a local authoritative entrance, and serve the urban life circle for the people, inject the brand value of the traditional brand "Jianghanfeng", integrate the news, government affairs and services of the province, city and county, and also launch multiple models such as newspapers, contributions, and circles, so as to diversify and enrich the user experience.