The latest progress of Shenhai Expressway!

author:Rizhao Daily

The Rizhao section of Shenhai Expressway is an integral part of the "Longitudinal No. 2" line of the national highway network. During the May Day holiday, the construction personnel gave up rest, adhered to the front line of construction, paid attention to quality, ensured safety, and caught up with the schedule, so as to ensure that it was completed and opened to traffic by the end of the year.

In the prefabricated beam yard of the first bid section of the reconstruction and expansion of the Rizhao section of the Shenhai Expressway, workers are busy making large reinforced concrete prefabricated parts such as box girders and panels of various specifications.

The latest progress of Shenhai Expressway!

Shenhai Expressway Rizhao Section Reconstruction and Expansion of a Bid Section of Prefabricated Beam Field Technician Yuan Xuefeng: At present, the process we are doing is the process of 30 meters of prefabricated box girder outer membrane, under normal circumstances, it is 2 pieces of prefabricated box girder a day, 5 pieces of 20-meter hollow slab a day, 6 pieces of 16-meter hollow slab a day, 5 pieces of 8-meter and 6-meter solid slabs can be completed in a day, a total of about 18 pieces a day.

It is necessary not only to be strict with quality, but also to catch up with the schedule, but also to ensure safety. During the "May Day" holiday, the workers of the prefabricated box girder yard worked in shifts day and night to ensure the front-line construction needs of the project.

The latest progress of Shenhai Expressway!

Yuan Xuefeng, technician of the prefabricated beam yard of the first bid section of the reconstruction and expansion of the Rizhao section of the Shenhai Expressway: In order to complete the task faster, we have increased equipment, increased personnel, ensured quality, and strictly followed the requirements of the specification (construction), which can currently meet the erection needs of the box girder of the superstructure on the site (project).

The Futuan River Bridge is the bridge with the largest span in the reconstruction and expansion project of the Rizhao section of the Shenhai Expressway. At present, the substructure of the bridge has been fully completed, and the girder erection work is underway.

The latest progress of Shenhai Expressway!

Xu Li, deputy manager of the project department of the reconstruction and expansion of the Rizhao section of the Shenhai Expressway: The Fu Tuan River Bridge is the longest span bridge on the whole line, with a total length of 586 meters, and the geology of the Fu Tuan River is also relatively complex, and the granite below is relatively hard.

The Rizhao section of Shenhai Expressway was completed and opened to traffic in 2003, and with the continuous and rapid growth of traffic volume, it has far exceeded the original design traffic volume, and it is urgent to improve the traffic capacity through reconstruction and expansion.

As a major provincial and municipal key project to start construction in 2023, the reconstruction and expansion project of the Rizhao section of the Shenhai Expressway starts from the Rizhao boundary of Qingdao in the Shanhaitian Tourism Resort in the north and ends at the Lusu boundary of the Xiuzhenhe Bridge in Lanshan District, with a total length of 61.7 kilometers, from the original two-way 4 lanes to two-way 8 lanes, with a design speed of 120 km/h.

The latest progress of Shenhai Expressway!

Meng Lingchang, head of the construction office of the first bid section of the reconstruction and expansion of the Rizhao section of the Shenhai Expressway: The project (bid section) has invested a total of 785 labor personnel and 267 sets of various machinery and equipment, forming a bridge technology and substructure, beam and plate prefabrication and installation, subgrade earthwork filling, pavement washing and planing, existing bridge demolition, existing bridge reinforcement and other construction of a big dry scene.

The reconstruction and expansion project of Rizhao section of Shenhai Expressway has 13 bridges, 9 interchanges, 20 separate interchanges, 1 service area, 1 maintenance area and 5 ramp toll stations. Up to now, 23.0% of the roadbed project has been completed, 21.2% of the bridge and culvert project has been completed, and 5.4% of the housing construction project has been completed. The implementation of the project is of great significance to promote the integration of the Jiaodong Economic Circle, improve the service level of the Shenhai National Highway Transportation Corridor, and accelerate the economic development along the route.

Source: Rizhao News