April is infinitely bright, and it is the time to forge ahead. Since April, a number of projects under construction of Baoye Steel Structure have ushered in new breakthroughs in nodes.

The progress of Baoye Steel Structure under construction has made breakthroughs

Above: Changchun Film and Television Cultural and Creative Incubation Park Project

On April 16, the Changchun Film and Television Cultural and Creative Incubation Park project ushered in the first lifting task of the main truss in the 2024 Jiachen Dragon Year, and the 63-meter-long dragon was watched by all the staff of the project, and the main truss rose in the warm spring breeze, and finally sat on the top of the A-43 axis giant steel column on the north side of the ice and snow photography base, marking that the project is about to fully enter the roof pipe truss steel structure installation stage.

The second phase of the construction project of Changchun Film and Television Cultural and Creative Incubation Park is located in Jingyue High-tech Industrial Development Zone, Changchun City, Jilin Province, with a total area of 248,000 square meters and a total construction area of 473,000 square meters.

The progress of Baoye Steel Structure under construction has made breakthroughs

Above: Above-ground steel structure project of Dishui Lake Financial Bay Phase II Project (Plot 03-01) in Lingang New Area

On April 20, the above-ground steel structure project of the second phase of the Dishui Lake Financial Bay Project (plot 03-01) in the Lingang New Area was successfully hoisted for the first time, and the project construction officially entered a new journey.

The steel structure project of Dishui Lake Financial Bay Phase II Project (Plot 03-01) of Lingang New Area is located in Lingang New Area, Nanhui District, Shanghai, east of Shuiyun East Road, west of Huanhu East Road, north of Bingang Avenue, south of planned Yinbai Road, the project is located in Lingang New Area 03-01 plot, the nature of the land is office, with a total land area of about 21,000 square meters and a total construction area of 94,000 square meters.

The progress of Baoye Steel Structure under construction has made breakthroughs

Above: Library (A1) project of Liangxiang Campus of Beijing University of Chinese Medicine

On the morning of April 21, as the first steel column slowly rose, and then fell accurately in the design position, the steel structure of the library (A1) project of Liangxiang Campus of Beijing University of Chinese Medicine was successfully hoisted for the first time, and the project set off a big upsurge.

The library project of Liangxiang Campus of Beijing University of Chinese Medicine is located in Fangshan District, Beijing, with 2 underground floors and 7 floors above ground, with a total construction area of 62,000 square meters, including 42,000 square meters of underground construction area.

The progress of Baoye Steel Structure under construction has made breakthroughs

Above: A new project with an annual output of 7.3GWh cylindrical lithium-ion batteries

On April 22, with the completion of the installation of the last color steel plate, the second bid section of the new project with an annual output of 7.3GWh cylindrical lithium-ion battery was crowned with gold, realizing the transformation of the project's focus from the main construction of the steel structure to the construction of the enclosure structure.

The total construction area of the project is about 99,700 square meters, with steel structure and frame structure, with a maximum span of 31 meters, a height of 22.4 meters, and a maximum single area of 53,000 square meters.

The progress of Baoye Steel Structure under construction has made breakthroughs

Above: North China Electric Power University Sports Center Project

On the morning of April 26, the main steel structure of the sports center project of North China Electric Power University was successfully capped, marking the official entry of the stadium into the stage of decoration and decoration engineering.

The North China Electric Power University Sports Center project is located on the campus of North China Electric Power University, Changping District, Beijing. The sports center adopts the intensive layout mode of integrating venues, and increases the area of the sports field from the existing 20,200 square meters to more than 64,500 square meters through the organic coordination and linkage layout of the ground, ground and underground under the condition that the land area remains unchanged. After completion, the sports center will provide indoor sports venues, standard track and field football fields, wind and rain running corridors and more than 300 underground parking spaces for teachers and students of the school, which can meet the needs of various sports activities such as swimming, basketball, badminton, volleyball, table tennis, fitness, martial arts, taekwondo, large-scale conferences, theatrical performances and so on.

The progress of Baoye Steel Structure under construction has made breakthroughs

Above: Wenzhou Cultural Exhibition Center project

On the morning of April 27, with the gentle lifting of the first section of the box column in the basement, firecrackers and fireworks, after rapid adjustment of the steel column support in place, the first section of the box column of the steel structure project of the Wenzhou Cultural Exhibition Center project was successfully hoisted, marking the project officially entered a new stage of main construction.

The Wenzhou Cultural Exhibition Center (G-08 Plot) project is located in the G-08 plot of the business center unit in the core area of Wenzhou City, with the Convention and Exhibition Center in the east, Huizhan Road in the south, G-08 in the west, and Oujiang Road in the north. The total land area is 48,000 square meters, and the total construction area is 71,000 square meters.

The progress of Baoye Steel Structure under construction has made breakthroughs

Above: The new Shenzhen Cultural Center project

On the morning of April 27, the new hall project of Shenzhen Cultural Center successfully completed the installation of the last whole hoisting truss, marking another successful step in the perfect performance of the steel structure of the project, and making the final sprint stage for the subsequent cantilever structure and the installation of the steel structure of the three theaters.

The new Shenzhen Cultural Center project is located in Longhua District, Shenzhen, Guangdong Province, with a total construction scale of about 88,100 square meters. The new museum is positioned as "the center of the Bay Area, a benchmark in China". Integrating education, exchange, training, performance, exhibition, cultural and creative functions, it is a comprehensive cultural landmark building with the nature of public welfare mass cultural services covering various groups and various art categories.

The progress of Baoye Steel Structure under construction has made breakthroughs

Above: Binjiang Road Rapid Reconstruction Construction Project

On April 28, the steel box girder of the main line of the Huangtiangang Bridge in the BJ-SG-2 bid section of the Binjiang Road Rapid Transformation Construction Project was completed three days ahead of schedule, marking a major phased victory in the construction of the project and laying a solid foundation for the subsequent opening of the whole line.

Binjiang Road is an important part of Jiangyin's urban expressway network, and the section of the Binjiang Road Rapid Transformation (Urban Section) construction project BJ-SG-2 across the Xicheng Canal (Huangtian Port Bridge) is a double-layer structure, including a viaduct and a ground bridge. The steel box girder of the viaduct Huangtiangang Bridge was constructed by Shanghai Baoye, including the 36th main line steel bridge, the LA ramp steel bridge on the north side, and the LB ramp steel bridge on the south side, all of which are three-span continuous variable section steel box girders, with a span diameter of 74.5 + 105 + 74.5 meters. The above-ground bridge is a four-beam arch bridge.

Drumming urges the boat to stabilize and set sail for a new journey. Baoye Steel Structure will continue to overcome difficulties, work hard, make every effort to tackle the major difficulties of the project, comprehensively promote safety production management, practice the corporate mission of "building high-quality projects and casting evergreen foundations", continuously promote lean construction and quality performance, and promote the high-quality development of the steel structure construction industry.