24 years of second-level constructor mechanical and electrical pure gold test center escalator acceptance, the second construction must test center

author:Let's learn it

1. Civil engineering handover and acceptance(1) The construction unit, the supervision unit, the civil engineering unit, and the installation unit jointly participate in the acceptance of the civil engineering and go through the handover procedures.

(2) There must be a railing or barrier around the shaft to ensure safety, and its height is strictly prohibited to be less than 1.2m.

(3) According to the passage and handling space required for the elevator equipment to enter the site provided by the elevator equipment supplier, check and confirm whether there is enough space for the transportation and hoisting of the truss.

24 years of second-level constructor mechanical and electrical pure gold test center escalator acceptance, the second construction must test center
24 years of second-level constructor mechanical and electrical pure gold test center escalator acceptance, the second construction must test center

Tips→ Safety protection acceptance

Escalators and moving walks must automatically stop operating when there is no control voltage, circuit ground fault, or overload. If escalators and moving walks stop operating in the following cases, the switch must be disconnected by means of safety contacts or safety circuits.

24 years of second-level constructor mechanical and electrical pure gold test center escalator acceptance, the second construction must test center

(1) The step or pedal sags, or the tape enters the comb plate where there is a foreign object clamping, and the step, pedal or tape support structure is damaged.

(2) Parts (such as chains or racks) that directly drive steps, pedals, or tapes are broken or excessively elongated.

(3) The control device operates under the overspeed and non-manipulation reversal of the running direction.

(4) One of the multiple escalators (moving walks) installed in a row without an intermediate exit is out of operation.

(5) Additional brake action. (6) The distance between the drive and the steering device is shortened (unintentionally). (7) Handrail with entrance protection device action.

Shorthand: No electricity overload is not safe

[striking while the iron is hot] 1. When the moving pavement enters the site for acceptance, the parts that must have a copy of the type test report are ( ).

A.踏板B.护壁板C.盖板D.围裙板

2. ( ) is not included in the random documents for the acceptance of elevator equipment.

A. Elevator installation plan B. Equipment packing list C. Electrical schematic diagram D. Civil engineering layout drawing

3. The load of the elevator progressive safety gear action test is ( ).

A. 50% rated load B. 100% rated load C. 110% rated load D. 125% rated load capacity

4. In the following escalator faults, the switch disconnection must be completed by the safety contact circuit ( ).

A. No control voltage B. Ground fault C. Circuit overload D. Pedal sagging

本节答案: 1. A 2. A 3. D 4. D