Tireless leader, He Jincheng went all out to escort the construction of the Jishang Expressway project

author:Qilu one point

The May Day holiday is approaching, and the workers, who have long been accustomed to running at work, are still fighting day and night. They revolve around the project, concentrate on the project, and go all out to improve the quality and efficiency of construction.

He Jincheng, deputy general manager of China Energy Gezhouba Jiaotou Jishang (Jining) Company, is one of them. In the promotion of the project, he not only grasped the communication and coordination of all parties, applied for approval of the procedures, but also rushed to the front line of construction without blind spots to inspect and guide, and control the progress, quality and safety of the project. Under his leadership, the construction land approval was obtained 6 months after the project was launched, and all node goals were completed ahead of schedule, creating a "business speed".

Concentrate on the project Tackling control projects

"According to last week's scheduling meeting, the relevant exhibition boards, civilized construction management and the preparation of special plans for cable-stayed cable construction have been implemented. However, the progress of the backfill of the Jinxiang South Hub Interchange Station and the reconstruction of local roads is lagging behind, so it is necessary to pay more effort and complete it on time. In addition, at the next week's meeting, the construction unit should prepare a construction traffic control plan for the cross-embankment section to ensure construction safety and social traffic safety, clarify the construction period and smooth plan, etc., and be sure to complete the review before April 26. On April 23, He Jincheng came to the construction site early and clarified the construction progress and key points of this week with the construction unit, monitoring unit and other parties. "For the new Wanfu River bridge project in the Jining section of the Jishang Expressway, we will hold a scheduling meeting every Friday to clarify the key points of construction and ensure the progress of the project. He Jincheng said.

Tireless leader, He Jincheng went all out to escort the construction of the Jishang Expressway project

It is understood that the Jining section of the Jining section of the Jishang Expressway project route starts from Jiaxiang County, Jining City, and ends in Jinxiang County, with a total length of 45.06 kilometers, adopting the two-way six-lane expressway standard and a design speed of 120 kilometers per hour. The project is a key project of the "14th Five-Year Plan" of Shandong Province, a provincial major project, and a first-class key project of the municipal wall chart operation. Among them, the main span of the new Wanfu River Bridge is 185 meters long and 35.5 meters wide, which is the control project in the whole project, and its construction progress determines the opening time of the Jining section.

"The bridge deck of the new Wanfu River Bridge adopts a whole design, which is a single-box three-room structure with a large single volume. Shi Yaqiang, head of the engineering management department of China Energy Gezhouba Jiaotou Jishang (Jining) Company, said that compared with the slatted structure, the whole bridge structure is complex, the process is cumbersome, and the construction time is longer. Therefore, Mr. He not only often holds meetings with general contractors and supervisors to discuss construction technical plans, on-site problems, plan construction nodes and key points, but also often climbs to the front line of the bridge deck to inspect the on-site construction progress, quality, and safety issues one by one. ”

From the ladder to the towering bridge deck, workers are installing steel bars, prestressed pipes, and everything is in order. "How long have you been here? How are you working and eating? Is the salary paid normally?" He Jincheng walked into the ranks of workers and chatted with everyone. "I'm from Hubei, I was on the project last year, and I rushed over after the Spring Festival resumed work this year. Master Hu, who was tying steel bars, said that the construction work was hard and far from home, but fortunately, the salary was good. As he spoke, he took out his mobile phone to show, "The average monthly salary is about 10,000, and the payment is timely, I am quite satisfied." Master Hu said.

Co-ordinate forces and integrate resources Create "business speed"

In addition to the new Wanfu River Bridge, the project also includes bridges, middle bridges, separation interchanges, passages, culverts, etc., among which the more difficult problem is the problem of subgrade earthwork filling soil source. Due to the section from Jiaxiang to Jinxiang, the terrain is relatively flat, and the two counties are large agricultural counties, many of which are basic farmland, and the land resources are precious. This section of the road requires a total of about 10.6 million square meters of land, which is a key problem restricting the project to be opened to traffic on schedule.

"We actively communicate with the governments of Jinxiang County and Jiaxiang County of Jining City, keep an eye on the top, list-based management, and daily and weekly inspections. He Jincheng said that many parties brainstormed and finally agreed to meet the needs of the project through the comprehensive use of other project spoils, river dredging earthwork, and the construction of Yangshan Reservoir spoil. "The soil does not fully meet the construction standards, and it must be improved by adding lime or cement to improve the quality of the roadbed fill. ”

Tireless leader, He Jincheng went all out to escort the construction of the Jishang Expressway project

He Jincheng joined Gezhouba Group in 1999 and has grown from a technician to a person in charge today, who he said is inseparable from the platform and environment provided by the company, and at the same time, individuals also need to continue to learn and improve their practical ability and ability to deal with complex problems. The change of position also brings about a change in the content of work. In the past, we only needed to focus on our own work, but now we should not only pay attention to the construction progress, quality and safety, but also do a good job in the coordination of local relations, the supervision of migrant workers' wages and other factors, and do a good job in overall project construction management.

"Mr. He has a lot of things, but he has never stopped to the front line of construction. In the process of promoting the project, he is often not required to visit the site in person, but even if there is no major node, he still visits the project 4-5 times a week for inspection and guidance, and spares no effort for the construction of the project. Li Chong, head of the third standard construction area of Jishang Expressway, said.

Thanks to the joint efforts of everyone, the project node goals have been completed ahead of schedule, among which, 1 month to achieve the main line of all the clearing, 33 days to complete the bill of quantities signing, 2 months to complete the new Wanfu River Bridge main pier pile foundation, 3 months to achieve the first box girder pouring, 4 months to achieve the first box girder erection, creating a "business speed".

The May Day holiday is approaching, and He Jincheng, who follows the project all the year round and gathers less with his family, is ready to stare at the key nodes of the holiday, and then arrange a break. "My family is in Wanzhou, Chongqing, and I have two children at home, the eldest daughter is in the second year of junior high school, and the younger son is 6 years old this year. On May 8th, my youngest son celebrated his birthday, and he kept yelling that I would go home to accompany him, and this time I was going to take the time to go back to celebrate his birthday. He said that over the years, he has returned home once a year, and his wife and children have gradually become accustomed to the long separation. High-quality companionship when you get together, leave a happy and good time, and you won't have too many regrets after separation.

However, He Jincheng changed his tone and focused on the project again. He said that the relevant construction nodes have been clearly deployed. "We will anchor the goal of opening to traffic in 2025 and plan ahead, start housing construction and water stabilization paving construction before May Day this year, start asphalt paving construction at the end of June, and start traffic safety, mechanical and electrical, and greening construction at the end of October, so as to promote the construction of the project with high quality and efficiency. ”