The Qingong all the way through the salty copper railway project is expected to be completed by the end of the month

author:JingLvZiXun

As an important nodal project of transportation facilities around the Qinhan Museum of Shaanxi Libo, the Qingong Road through the Xiantong Railway Project is currently jacking the box culvert at a speed of 7 meters per day, and the jacking construction is expected to be completed at the end of the month.

In order to welcome the 2024 "5.18 International Museum Day" in China, the main venue event was held in the Qinhan Museum of Shaanxi Libo, at the end of last year, the Qinhan New City started the improvement of the surrounding environment of the museum and the construction of supporting facilities.

The Qingong all the way through the salty copper railway project is expected to be completed by the end of the month

The project is located at the intersection of Qingong 1st Road and Xiantong Railway, designed to use a 5-hole box bridge to cross the railway, the middle hole is a comprehensive pipe gallery channel, the box culvert is 8 meters wide, and two holes on each side are arranged with two-way 6 lanes and non-motorized lanes and sidewalks, with a box culvert width of 12 meters + 5.5 meters, and the construction content includes roads, lighting and traffic engineering.

The Qingong all the way through the salty copper railway project is expected to be completed by the end of the month

"At present, there are nearly 200 front-line construction workers on site, who are carrying out box culvert jacking, ramp construction and other operations. It is expected that after the completion of the box culvert jacking at the end of April, it will enter the pavement construction stage. The person in charge of the project site introduced.

The Qingong all the way through the salty copper railway project is expected to be completed by the end of the month

It is understood that the box culvert of the salty copper railway is prefabricated all the way through the Qingong and then jacked by the construction method, which is pushed from north to south.

The Qingong all the way through the salty copper railway project is expected to be completed by the end of the month

"Since the start of the project, the participating units have actively coordinated and optimized the construction plan, and made full use of the train running skylight period to carry out construction to ensure that the construction of the project is progressing steadily according to the time node. The project leader said.

The Qingong all the way through the salty copper railway project is expected to be completed by the end of the month

After the completion of the Xiantong Railway Project, Qingong 1st Road will go north through Metro Line 14 and Xiantong Railway, and connect with Lanchi 3rd Road through the ramp. At present, the interchange project located on the south side of the railway has completed the asphalt paving and marking of the road surface, and has the conditions for opening to traffic.

The Qingong all the way through the salty copper railway project is expected to be completed by the end of the month

After the completion of the transportation supporting project around the Qinhan Museum of Shaanxi Libo, it can comprehensively solve the interconnection of Jingwei Avenue, Lanchi Avenue, Lanchi 2nd Road, Lanchi 3rd Road, and Qingong Station of Metro Line 14, forming a traffic loop, connecting the protection of cultural relics and cultural tourism projects such as Qinhan Museum, Qin Civilization Square, Qinxianyangcheng National Archaeological Site Park, and Dahan Purple Road, so as to meet the travel needs of tourists and the surrounding people. (Source: Qinhan New Town)