Spring glows with a new look and family letters are beautiful
Poly and Guangchenyue April project progress broadcast
Dear Poly and Guangchenyue families,
Seeing the words is like meeting, and the letter is comfortable. Flowers are blooming, and the earth is new.
The warm wind blows the prologue of all things, and the longing for happiness is slowly brewing in the greenery of late spring. Our home is growing in a growing attitude, presenting excellent quality in the architectural context, with the same original intention, carefully carved a brick and tile, a grass and a tree, just to perfectly present your heart's desire, on the occasion of the warm spring, a paper of home sound, may you be warm and at ease in the days of waiting, and invite you to open the new look of your home.
Please read the latest project progress
1#
The main body has been capped, and the roof has been handed over to the exterior wall for construction
Floors 1-21 are completed with floor heating, and 3-21 floors are scraped white
Exterior wall insulation 100% completed, paint 100% finished
Window installation is 100% complete, glass installation is 80% complete
2#
The main body has been capped, and the roof has been handed over to the exterior wall for construction
1-20 floors of floor heating are completed, and 3-20 floors of whitening are completed
Exterior wall insulation 100% completed, paint 100% finished
Window installation is 100% complete, glass installation is 80% complete
3#
The main body has been capped, and the roof has been handed over to the exterior wall for construction
4-23 floors of underfloor heating are completed, and 17-23 floors of whitewashing are completed
Window installation is 100% complete and glass installation is 70% complete
4#
The main body has been capped, and the roof has been handed over to the exterior wall for construction
4-23 floors of floor heating are completed, and 18-22 floors of whitening are completed
Exterior wall insulation 5% complete, window installation 100% complete
Glass installation 70% complete
5#
The main body has been capped, and the roof has been handed over to the exterior wall for construction
Floor heating is completed on the 1st-23rd floor, and 6-23 floors are scraped white
Exterior wall insulation 100% completed, paint 100% finished
Window installation is 100% complete, glass installation is 80% complete
6#
The main body has been capped, and the roof has been handed over to the exterior wall for construction
Floor heating is completed on floors 1-23, and floors 3-23 are scraped white
Exterior wall insulation 100% completed, paint 100% finished
Window installation is 100% complete, glass installation is 80% complete
7#
The main body has been capped, and the roof has been handed over to the exterior wall for construction
7-21 floors of floor heating are completed, and 18-22 floors of whitewashing are completed
10% exterior wall insulation and 100% window installation
5% Glass Installation Complete
Project address: south side of Taihang West Street Hydraulic Plant, Luzhou District