"Look at Xianyang" News: In the early morning of April 22, the Weiyang Middle Road Rain and Sewage Diversion Reconstruction Project constructed by the Ninth Company of Shaanxi Construction Sixth Construction Group successfully completed the construction task and delivered a satisfactory answer sheet for the people of Xianyang.

Shaanxi Construction Liujian Group | Speed up and speed up, the rain and sewage diversion transformation of Weiyang Middle Road was completed ahead of schedule!

Weiyang Middle Road (Qinhuang Road - Leyu Road) is located in the middle of the main urban area of Xianyang City, the road grade is the main road of the city, the design scope of Weiyang Middle Road rain and sewage diversion reconstruction range from Qinhuang Road in the west, through Tuanjie South Road, east to Leyu Road, the total length of the design is about 1240m, and the width of the current road red line is 40m. After the renovation, the width of the existing roadway and sidewalk will not be changed, and the current road plane will be maintained.

Shaanxi Construction Liujian Group | Speed up and speed up, the rain and sewage diversion transformation of Weiyang Middle Road was completed ahead of schedule!

The project has a tight schedule and heavy tasks, and the contract period has been reduced from the original 180 days to 70 days. After receiving the construction task, the nine companies immediately organized elite soldiers to be stationed at the construction site, and the manager personally went to the construction site to deploy the construction task, clarify the closing time of large nodes, the entry time of key materials and the node requirements of the relevant unit time, and the responsibility was clearly implemented to the person.

Shaanxi Construction Liujian Group | Speed up and speed up, the rain and sewage diversion transformation of Weiyang Middle Road was completed ahead of schedule!

In order to achieve the project duration and quality goals, in the process of project construction, the nine companies continue to improve their political position, overcome all difficulties, and always maintain 24-hour shift operations. In view of the construction of important divisions, sub-projects or key processes and special processes, combined with the technical characteristics and difficulties of the project, prepare special construction plans or work instructions; organize technical personnel to tackle key problems, change the original supporting wall plate from three sections to two ends of construction, and change the water stabilized layer of the working pit and working well to pouring concrete, which greatly shortens the construction period; scientifically and rationally organize the construction, strengthen the process quality control, and strictly implement the relevant systems such as the "three inspection system", the model guide and the actual measurement, so as to achieve the one-time success of the project.

Shaanxi Construction Liujian Group | Speed up and speed up, the rain and sewage diversion transformation of Weiyang Middle Road was completed ahead of schedule!

During the construction, Shaanxi Construction Sixth Construction Group No. 9 Company has always adhered to the corporate philosophy of "building for good", fully carried forward the spirit of the iron army that is not afraid of hardship and tiredness, and is brave and good at fighting, after 60 days and nights of fierce battles, the construction period was advanced by 10 days again, and the construction tasks were successfully completed in advance at 0:00 on the 22nd, and the full opening of traffic was realized, making positive contributions to the early opening of the lighting project in Xianyang City and Daqin Sleepless City.