Recently, it was reported that the construction period plan of Tianjin Lishen New Energy Technology Co., Ltd. - Binhai New Energy Base Construction (Phase I) with a total investment of more than 3.2 billion yuan was exposed.
Renderings @ Lishen battery
The project is located in the Marine Science and Technology Park of Tianjin Binhai High-tech Zone, east to Tianjin-Qin high-speed railway, west to Haide Road, south to Guoxiang West Road, north to Tianxiang West Road, near Binhai West Railway Station, with a total construction area of about 156385 square meters, including battery cell workshop, comprehensive service building, electrolyte warehouse, fire pump room and pool, sewage treatment station, hazardous waste warehouse, power station, finished product warehouse, 110KV substation, etc., with a total investment of 325327 million yuan.
Publicity map @ Tianjin High-tech Zone
It is reported that the total planned investment of Lishen Binhai New Energy Base project is about 10 billion yuan, with a total construction area of about 400,000 square meters, which will be implemented in three phases.
Renderings @ China Machinery International
According to the project supervision bidding announcement released this time, the planned construction period of the first phase of the project is from June 30, 2024 to September 30, 2025. (Synthesized from Tianjin Construction Engineering Information Network, Tianjin High-tech Zone, Binhai Release)