What's New!
Nanshan Dragon Ball Avenue
It will be transformed into a hub gateway boulevard
How will the project be implemented?
How many phases are there in the construction?
What is the impact of the construction process on the travel of Nanshan people?
Let's take a look
Longzhu Avenue will be transformed into a hub gateway avenue
The Longzhu Avenue Comprehensive Renovation and Blackening Renovation Project is located in the Longzhu area of Taoyuan Street, starting from Longjing Road in the west to the Longzhu Interchange of Beihuan Avenue in the east, with a total length of about 4,000 meters and two-way eight lanes, which is the main road of the city.
Schematic diagram of Longzhu Avenue (subject to actual conditions)
The project will build Longzhu Avenue into a hub gateway avenue through road section reconstruction, traffic organization optimization, place building, smart empowerment, pipeline expansion and other means, so as to achieve a green, safe, efficient and intelligent travel experience, create a "warm" urban public space, and better serve residents along the route.
Longzhu Avenue is undergoing construction on the inverted edge of the road
The reporter learned from the Nanshan District Construction and Public Works Department that in order to ensure the smooth progress of the comprehensive renovation and blackening renovation project of Longzhu Avenue and avoid traffic congestion, the project is occupying the road for inverted construction, please understand and support the public.
It is reported
The project is divided into three construction phases
Carry out the construction of occupying the road and chamfering
The first stage of the reversing of the road
The main construction content is the construction of underground pipelines such as water supply pipes on the north side and sewage pipes on the south side of Longzhu Avenue, and excavation and burial pipelines are required at all traffic intersections.
Construction period
March 20, 2023 to May 31, 2024
The second stage of the inverted side of the road
The main construction content is the central green belt of Longzhu Avenue, the landscape improvement of the green belt on the north and south sides, and the pavement of the slow traffic system.
Construction period
October 27, 2023 to July 27, 2024
The third stage of the road reversal
The main construction content is road milling and asphalt pavement, intelligent and traffic safety facilities construction.
Construction period
April 2, 2024 to November 2, 2024
The District Construction and Public Works Department said that due to the needs of the construction process (process), the project will bring inconvenience to citizens and friends during the implementation process, please understand and support. The department has taken measures to speed up the construction, strive for early completion, and promptly address the reasonable demands of citizens and friends during the construction process.
Roads are the lifeblood of a city
It not only brings convenience to people's lives
It also drives the future development direction of the city
Let's look forward to the upgrade of Dragon Ball Avenue butterfly~
来源 | 蛇口消息报 记者 | 刘野
编辑 | 黄锦彤 责编 | 董非
Audit | Liang Yashu and Lu Dongbo
Please indicate the above information for reprinting
Some of the pictures in this WeChat article may come from the Internet
If your rights and interests are infringed, please contact us in time to delete it
The opening of traffic is imminent, Shenzhen ⇆ Meizhou 1.5 hours round trip!
What's it like to be a tech blogger with 6 million followers?
When the robot has a "smart brain"