laitimes

China's first asymmetrical phased turnaround bridge "and blossom"

author:MOB推荐

April 11th

At the confluence of Kunshan's "mother river" Loujiang River and Qingyang Port

A 1,750-ton oversized steel arch tower

Under the action of traction equipment

It blooms like a "and dilian" on the clear waterway

It marks the construction undertaken by China Construction Seventh Bureau

The highest inland river bridge in Suzhou - Kunshan Zhenchuan Bridge Project

Smooth vertical rotation

Witnessing the Seventh Bureau of China Construction and Kunshan City

Work together to promote the upgrading of Kunshan's waterway industry and human settlements

Go hand in hand, and blossom together.

China's first asymmetrical phased turnaround bridge "and blossom"

Kunshan Zhenchuan Bridge Project is a major traffic and water transportation project in Jiangsu Province, and is an important part of the waterway improvement project of Qingyang Port section of Shenzhang Line, starting from the level crossing of Heilongjiang Road, spanning Qingyang Port on the route, with a total length of 931 meters, of which the bridge is 507 meters long and the main bridge is 230 meters long. As an important part of Kunshan's "five districts and one line" planning, the project is difficult to construct, install, hoist and turn, and will make the Qingyang Port channel have the transportation capacity of thousand-ton container ships, effectively helping Kunshan's "urban living room" to build and improve the comprehensive transportation system.

The volume is large, challenging the most in Jiangsu Province

As a "star project" in Suzhou's bridge industry

Zhenchuan Bridge is currently in Jiangsu Province

The rotating weight of the steel tower of the same steel structure cable-stayed bridge is the largest

The bridge is a cable-stayed bridge with asymmetrical steel arch towers

The total weight of the large and small steel arch towers of the main bridge is about 3,100 tons

This puts forward extremely high requirements for the bearing capacity and construction technology of the bridge foundation.

China's first asymmetrical phased turnaround bridge "and blossom"

The project team sought a breakthrough from the technical level

After many in-depth discussions and repeated demonstrations

Facing on a river channel more than 200 meters wide

The main bearing platform with a total amount of concrete to be poured exceeds 4,000 square meters

It was determined that "the substructure pile foundation cofferdam built the island."

+ cushion cap steel sheet pile support + main pier shaped steel mold construction".

China's first asymmetrical phased turnaround bridge "and blossom"

The construction personnel planned and organized in advance

Continuance of Overcoming Geographical Conditions

Fill the river 90 meters on the east side of the river with clay

Use an excavator to dig the earthwork in the steel sheet pile of the cap to a depth of 10 meters

The cushion cap formwork uses ordinary large steel molds

Crawler crane is used for hoisting.

China's first asymmetrical phased turnaround bridge "and blossom"

Operators enter the foundation pit in Hanoi to carry out manual bottom cleaning

In the face of its internal steel and steel structure intricate,

The situation that the concrete vibrating is inconvenient

Binding of rebar and pouring of large volumes of concrete in batches

The "prototype" of the bridge foundation was successfully completed.

China's first asymmetrical phased turnaround bridge "and blossom"

The main pier in the pit is a special-shaped variable cross-section

The construction is complex and extremely difficult

The requirements for installation control and positioning accuracy are extremely high

The project strictly debugs and controls the mix ratio of concrete

Externally, self-compacting concrete is used to pour in three phases

The condenser tube is set up to cool down according to the scheme

It adopts rigid skeleton, Fengzi board and prestressed material

Lay a solid foundation for the completion of the main bridge.

It is difficult to hoist, and strive for perfection to create a new landmark in Kunshan

China's first asymmetrical phased turnaround bridge "and blossom"

Zhenchuan Bridge is the history of Suzhou

The most difficult steel tower cable-stayed bridge to construct

The main body is composed of two parts: "steel box girder + steel arch tower".

If the steel box girder is the "torso" of the bridge deck

The steel arch tower is the "soul" of the bridge.

China's first asymmetrical phased turnaround bridge "and blossom"

The steel box girder is divided into 27 segments

The large and small steel arch towers are divided into 13 and 11 segments respectively

Its construction and installation quality and precision control

It directly determines the construction quality of the entire bridge

More than 50 steel structure segments

It is necessary to alternate multiple steps for batch transportation and hoisting on land and water

And it requires accurate installation and accurate points

The difficulty can be imagined.

China's first asymmetrical phased turnaround bridge "and blossom"

Due to the large lifting radius of the three sections on the east side

After the completion of the construction of the main pier of the bridge

The project uses a 90-metre-long land passage on the east side of the bridge

Two slides were laid for skid lifting

The 3 steel box girder segments are respectively hoisted to the sliding slideway and slid into place

At the same time, combined with the surface of the floating crane

It took 3 months to finally build a 130-meter-long steel bridge on the east side of the bridge

and the small steel arch tower and the preliminary work hoisting completed.

China's first asymmetrical phased turnaround bridge "and blossom"

It is different from the water and land hoisting on the east side

The bridge on the west side is 90 meters long

It is located at the intersection of Loujiang River and Qingyang Port

The water is turbulent, and it is more difficult to float on the water throughout the whole process.

China's first asymmetrical phased turnaround bridge "and blossom"

The project stabilizes the idea and divides the construction on the west side into two parts: north and south

After the completion of the steel box girder above the main pier

The lower section of the rotating tower is hoisted by floating crane

Subsequently, part of the steel box girder on the west side of the bridge was hoisted

Ensure that the south section of the large steel arch tower is assembled completely.

China's first asymmetrical phased turnaround bridge "and blossom"

After that, the steel pipe support on the north side is completed

Lift the remaining segments of the steel box girder and complete the bridge deck closing

Then hoisting the north side section of the large steel arch tower

Finally, a floating crane is adopted

Interspersed with the upper section of the turret gantry is hoisted

and install a cable wind rope

Make final preparations for the rotation of the small steel arch tower.

New technology, the country's first "asymmetric phase"

China's first asymmetrical phased turnaround bridge "and blossom"

The large and small arch towers of the project are 101 meters and 78 meters high, respectively

Tilt 25 degrees to the shore side, respectively

The arch tower is connected to the bridge deck by 30 cable-stayed cables

During the rotation process, the force of the arch tower will follow the progress of the project

and interleaved changes

Therefore, the vertical rotation is also in the process of the construction of the Zhenchuan Bridge

Critical processes with the greatest security risks.

China's first asymmetrical phased turnaround bridge "and blossom"

The project team adapts to local conditions

For the first time in the country, the asymmetrical phased rotation method was adopted

First, the large and small steel arch towers will be rotated in stages

Finally, the cables are installed in stages

The small tower is backed by the weight of the large arch tower itself

The arch tower is backed by 4 permanent structural cables

While ensuring safety, it also saves great costs.

China's first asymmetrical phased turnaround bridge "and blossom"
China's first asymmetrical phased turnaround bridge "and blossom"
China's first asymmetrical phased turnaround bridge "and blossom"

Before construction, the project department invites an expert group

Carry out in-depth exploration and research on the vertical rotation process

After more than 10 internal audits, the special construction plan has been continuously improved

During the construction process, the project uses "intelligent + manual" data to collect data in real time

Arrange inclinometers and strain gauges at the root of the bridge tower and in the chamber

Data such as speed and stress are monitored every 5 minutes.

China's first asymmetrical phased turnaround bridge "and blossom"

Combined with BIM models

The project monitors stress and deformation of critical parts in real time

Timely warning and correction of abnormalities are found

The attitude error of the steel tower is controlled between millimeters.

China's first asymmetrical phased turnaround bridge "and blossom"
China's first asymmetrical phased turnaround bridge "and blossom"

The jack works in a reciprocal cycle for 280 strokes

Each stroke averages 20 cm

The maximum tensile force of the steel cable is 729 tons

From April 10th, the turn began

After more than 30 hours of continuous construction

The large steel arch tower finally turned into place smoothly!