There is news of the resumption of roads around Line 6
Tomorrow (11 April)
Linton River Suspension Bridge Restoration Project
It's officially started
The editor reminds everyone
Plan your trip during construction
01
Project Overview
According to the construction progress of track line 6, it is necessary to reconstruct the Lindun River suspension bridge located at the intersection of the old school on Linton Road, the construction period is initially scheduled for April 11, 2024 to July 10, 2024, the old school and Linton Road were originally two-way two lanes, and part of the road surface will be occupied during the construction period.
Schematic diagram of the construction scope of the Lindun River suspension bridge
Preparations for the reconstruction of the suspension bridge are being carried out at the site, and the construction of auxiliary structures is being stepped up at the Suspension Bridge Lane Station and Lindun Road Station of Line 6 to speed up the return of the road to the people and smooth the roads in the ancient city.
02
Transportation organization program
The construction of the project is divided into two phases, the details are as follows:
(1) Phase I construction
Construction area: the southern half of the old school front
Construction period: April 11, 2024 - May 25, 2024
Traffic organization: The construction section of the old school suspension bridge maintains a one-way traffic from west to east, and non-motor vehicles and pedestrians still ensure two-way traffic.
Schematic diagram of traffic organization during the construction of the first phase
(2) Phase II construction
Construction area: the northern half of the old school
Construction period: May 25, 2024 - July 10, 2024
Traffic organization: The construction section of the old school suspension bridge maintains a one-way traffic from west to east, and non-motor vehicles and pedestrians still ensure two-way traffic.
Schematic diagram of traffic organization during the construction of the second phase
03
Advice on cross-border traffic
Motor vehicles going to the old school on Lindun Road can be transferred through Ganjiang Road, Renmin Road, Baitaxi Road and other roads.
Schematic diagram of the detour route for motor vehicles during construction
04
Improve traffic security facilities
In order to ensure the normal traffic during the construction period, the traffic police department, together with the rail transit group and the construction unit, has optimized and improved the traffic safety facilities around the construction area, and added construction traffic signs, warning signs, strobe lights, guardrails, etc.
Schematic diagram of the optimization of traffic safety facilities
Tips
During construction
Please follow the traffic signs
Choose a reasonable travel route and pay attention to traffic safety
Obey the command of the on-site duty personnel
We apologize for any inconvenience caused by the construction
Source: Suzhou Rail Transit
Editor: Xiao Ming