Re-investigation of the road construction puzzle (2) Who will pay for the project in the end?

author:Elephant News Client

Elephant News reporters Li Peng, Wang Haofeng, Li Yubo

Elephant News and Elephant Gang reported that Henan Guoyou Environmental Protection Technology Co., Ltd. (hereinafter referred to as Guoyou Company), Henan Houyunhao Construction Engineering Co., Ltd. (hereinafter referred to as Houyunhao Company), and Henan Industrial Construction Group Engineering Construction Co., Ltd. (hereinafter referred to as Gongjian Company) cooperated to carry out rural revitalization demonstration projects in Henan Province.

Re-investigation of the road construction puzzle (2) Who will pay for the project in the end?

Because of the alleged collection of construction enterprise project deposits in the Liuhua Administrative Village Project in Gaoji Township, Luyi County, Zhoukou City, the Gaoji Township Government suspects that this is a new type of scam.

Collecting the deposit for the quality of the project, Hou Yunhao Company does not know?

In addition to the fact that the organizer could not provide the construction procedures for the project, another important reason for the Gaoji Township Government to stop the Liuhua Village Rural Revitalization Demonstration Project was that Houyunhao Company collected a high project quality deposit from the construction team and borrowed money from the construction team, which was suspected of fraud.

In this regard, Guan Hongjie, the legal representative of Houyunhao Company at the time, said that he was very aggrieved. "How much money they pay has nothing to do with our Houyunhao company, we don't know, and we don't collect money. Guan Hongjie said, "We contracted all the projects to Zhoukou Haorun Construction Labor Co., Ltd., and there was no direct contact with the construction team below." ”

However, on this single construction contract, the reporter found that the third item above is marked with the terms of the contract performance fee: Party B (Zhoukou Haorun Construction Labor Co., Ltd.) pays 300,000 yuan to Party A (Henan Houyunhao Construction Engineering Co., Ltd.) The contract performance fee is 300,000 yuan, and the contract is paid 50,000 yuan on the day the contract is signed, and the contract performance fee is made up within 7 days after the contract is signed, otherwise it will be regarded as a breach of contract.

At the same time, the cooperation agreement signed by Houyunhao Company and Guoyou Company also indicates the terms of contract performance money: within 7 working days after the signing of the agreement, Party B (Houyunhao Company) will pay Party A (Guoyou Company) 100,000 yuan as a performance bond, and pay another 900,000 yuan within one month, a total of 1 million yuan, and 100% of the interest-free 100% will be returned to Party B within 3 working days after the agreement is terminated.

Re-investigation of the road construction puzzle (2) Who will pay for the project in the end?

Who pays for the project?

Whether it is a project quality deposit or a contract performance fee or a performance bond, it is all related to the project funds, so who will pay for such a project in the end?

Guan Hongjie explained: "We signed the agreement to package the materials manually, and according to the regulations on rural revitalization, we use state funds to leverage social funds, and we follow the reimbursement system. Therefore, the project is paid in advance by the construction team of our cooperative unit, and the single project is completed, and after acceptance, we submit the materials to the Guoyou Company, and the Guoyou Company applies for funding from the government. ”

Guo Jie explained: "The competent department for rural revitalization is the local agriculture and rural bureau, and the reporting process for all the materials is like this, which is called village declaration, township review, and county evaluation and storage. ”

Guo Jie, general manager of Guoyou Company, said that their rural revitalization demonstration project in Tuqiao Village, Zhaocun Town, Luoning County, Luoyang City, Henan Province, has been completed and is going through the appropriation process.

Re-investigation of the road construction puzzle (2) Who will pay for the project in the end?

Luoning County Agriculture and Rural Bureau: There is no such thing as applying for funds from above

On November 29, 2023, the reporter came to Tuqiao Village, Zhaocun Town, Luoning County, Luoyang City, Henan Province for field investigation.

Wei Jifeng, deputy mayor of Zhaocun town and secretary of the party branch of Tuqiao village, said that the first phase of the project has been completed, including the village's underground rainwater and sewage pipes and a sewage treatment plant with a daily processing capacity of 240 tons. For the quality of the work, they are very satisfied.

Zhou Lei, a technician of the company, said that the entire project cost about 20 million yuan, and all of it was completed by the construction company. As for where the money will come from and who will pay for it after the project is completed? As an engineering technician, he is not very clear.

Zhou Lei also said that at present, they are also carrying out the same project in three other villages in Zhaocun Town. Some have just started, some have been halfway through, and the amount of investment is similar to that of Tuqiao Village.

According to him, in Zhaocun Town alone, the industrial construction company will invest nearly 80 million yuan.

According to Guo Jie, the general manager of the previous Guoyou Company, the project of Tuqiao Village will eventually be accepted by the Luoning County Agriculture and Rural Bureau.

On the morning of November 30, 2023, the reporter came to the Agriculture and Rural Bureau of Luoning County, Henan Province. When explaining his intentions, Li Guodong, a member of the party group of Luoning County Agriculture and Rural Bureau and director of the Agricultural Industry Service Center, was very surprised: "We have heard of this project, but we have not participated in the project since its implementation, and we don't know what his project is all about." There is no such thing as us accepting and we applying for funds from above. Li Guodong also asked the reporter rhetorically: "Without preliminary research, feasibility analysis, project application, project approval, approval, bidding and other processes, build a project without authorization, and then ask the government for acceptance and funding, do you think it is possible?"

Re-investigation of the road construction puzzle (2) Who will pay for the project in the end?

(Li Guodong, member of the Party Leadership Group of Luoning County Agriculture and Rural Bureau and director of the Agricultural Industry Service Center)

Li Guodong recalled that regarding the Tuqiao Village project, Guoyou Company and Industrial Construction Company had jointly issued a "Report on the Promotion and Implementation of the Rural Revitalization Strategy" to the Luoning County Agriculture and Rural Bureau, hoping that the bureau would approve and seal it. After careful study, the county agriculture and rural bureau decided that there had never been such a precedent, so it did not sign and seal the application.

Li Guodong said that normal projects first need to be approved, and when the project is established, the source of funds should be explained, and after the project is approved, it is necessary to make an evaluation and financial review, and after the evaluation, public bidding will be carried out in accordance with the regulations, and then it will be implemented. The Tuqiao project did not go through the relevant procedures.

As for the acceptance of the project, Li Guodong said that the county agriculture and rural bureau did receive an invitation, but they refused. "We have never been involved in this project, and all the projects are underground pipe networks, and they have all been buried underground.

In the contract signed between Houyunhao Company and the construction company, the agreement on the payment of the project money is written as follows: after the single project is accepted by the government, the actual completed project quantity shall be reported in the current month, 70% of the completed project quantity shall be paid in the next month, and 27% shall be paid after 60 days, and the remaining 3% of the total project amount shall be paid as a warranty money, which shall be paid within 7 days (without interest) after the completion of the project for one year without quality problems.

The first condition for payment is that the government accepts the goods. However, as far as the Tuqiao Village project is concerned, the government has not participated in it, so how can it be accepted? Without the government's acceptance and acceptance, the construction company will not be able to get the project money.

Who will pay for the project in the end?

Elephant News and the Elephant Gang continue to pay attention.

If you have any questions

You can scan the QR code below for help with one click

Your "Anxiety and Sorrow"

Henan Radio and Television all-media reporters and relevant departments

Let's figure it out for you

Read on