What is stuck in the installation of the elevator schedule

author:Leju.com
What is stuck in the installation of the elevator schedule

The installation of elevators in the community would have been a good thing, but for the residents of the first unit of the first building in the guanghe district of Xingqing District, it has become a troublesome thing, and the elevator that began construction last year was not only delayed in completion, but also some problems, affecting travel.

The installation of elevators is a problem for unfinished residents to travel

Mr. Yao, a resident of the unit, told reporters that according to the requirements of the contract, they should have been able to use the elevator in mid-October last year, but by May this year, the project to install the elevator had not yet been completed. "The contract signed in August last year, which was said to be delivered in mid-October, has now been postponed by seven months and is still only halfway through construction." Mr. Yao said.

The reporter saw at the scene that there were wood and steel frames and other debris left by the construction around a unit, and after the corridor passage on the third and fourth floors was opened, there was a piece of glass that was not installed, and the corridor was only used to make a simple partition with objects less than half a meter high, and the corridors on the fifth and sixth floors had no protective measures.

Mr. Yao said that in such an environment, it is very worrying to enter and exit the unit building every day. "The corridor is only blocked with wooden planks, and sometimes the child will fall down with a little touch, which is very unsafe." The installation of the elevator has not been completed, and the safety problem has not been guaranteed, and Mr. Yao is very anxious. "I hope to be completed quickly, there are many children in the community, and it is easy to have problems back and forth."

The elevator company cannot install it until the civil construction is completed

In response to the problem of elevator installation, the reporter consulted Wang Haiying, sales manager of Ningxia Tongyu Elevator Manufacturing and Development Co., Ltd. Wang Haiying introduced that the installation of elevators in one unit of Building 1 is a contract signed with Ningxia Zhuoli Industry and Trade Co., Ltd., which mainly includes civil installation and steel structures, etc. At the same time, Ningxia Zhuoli Industry and Trade Co., Ltd. and Ningxia Tongyu Elevator Manufacturing and Development Co., Ltd. reached an agreement to purchase elevator equipment from the company.

Wang Haiying told reporters that at present, the civil work of Ningxia Zhuoli Industry and Trade Co., Ltd. has not been completed, and Tongyu Elevator cannot carry out the follow-up installation of the elevator. "Ningxia Zhuoli Industry and Trade Co., Ltd. only needs to wrap up the four pillars and the top on all four sides of the shaft, and we can install the elevator, and it will take a week to install the belt for commissioning."

The construction party expects to complete the construction this month

Why has the civil works been delayed? Cao Xiang, a staff member of Ningxia Zhuoli Industry and Trade Co., Ltd., also explained this in detail.

Cao Xiang said that last year's construction delay was because some residents did not pay the money in place, so they could only stand up the main body first, and then the residents completed the glass installation after handing over the money. The remaining works were originally scheduled to start in March this year, but due to the impact of the epidemic, construction did not start until April 10.

"The road surface has been restored after the shutdown last year, and we will speed up the construction process under the premise of ensuring safety." Cao Xiang said that it is expected to complete the civil works and replant the greenery by May 20, after which it will be withdrawn from the site and handed over to Tongyu Elevator for installation and commissioning. For the safety problems during the recent construction period, the company promised to arrange staff to strengthen management, do a good job in construction enclosure, and ensure the normal passage of residents.

【Easy to enjoy the purchase information, come and pay attention to Leju Network】

Source: Yinchuan Evening News

Premium content recommendations

Dongli District: Airport Avenue has a planned construction plan for the northern extension

Total price from 340,000! In April, the transaction details of Daquanzhou real estate were released! A map of property offers in May is attached

Pingdingshan Property Management Association issued a commendation A number of real estate properties were selected