Acceptance of the basic and main structure, and summary of the data that the supervisor needs to prepare

author:Ai 3D technology

First, the basic acceptance of the preparation matters

1. The quality supervision station will check: when the foundation is accepted, the local supervision department shall check the planning permission documents, construction permit documents and red line inspection certificates of the project. (The line is to be prepared by Party A) and the qualification of the construction unit, the superior supervisor checks the rectification record, and there must be a report if there has been a major accident. The project manager is present.

2. On-site acceptance must have: basic inspection batch acceptance records, sub-project acceptance records, division acceptance records, material testing and inspection reports, various programs, basic acceptance reports, supervision of the basic assessment report, basic acceptance notice, acceptance check-in form.

1. Foundation groove inspection records

2. Pre-inspection project records

3. Engineering positioning measurement and retest records

4. Foundation brazing records

5. Application for pouring foundation concrete

Sixth, the foundation concrete opening appraisal

7. Construction records of foundation concrete projects

8. Acceptance records of basic hidden projects

9. Quality acceptance record of the basic branch project

10. Quality acceptance record of earthwork sub-project

11. Quality acceptance record of backfill soil sub-project

12. Concrete sub-project quality acceptance record

13. Quality acceptance record of steel reinforcement sub-project

14. Quality acceptance record of masonry foundation sub-project

Fifteen, template sub-project quality acceptance record

16. Quality acceptance record of cast-in-place structure sub-project

3. Basic procedure: After the construction unit submits an application→ the construction unit \ supervision pre-inspection (including on-site physical buildings and data collation) → qualified, notify the quality inspection station \ design institute \ survey unit acceptance time→ formally hold the acceptance → after the acceptance is passed, several parties sign and approve.

Main points: The acceptance form of the foundation division (pile foundation sub-division), this acceptance form must be signed and sealed by Party A, supervision, design institute, survey unit, construction unit.

4. Other possible necessities

1) Overview of pile foundation engineering

2) Construction site quality management inspection records

3) Enterprise qualification, equipment, instruments, special type of work certificate

4) Construction organization design review form

5) Construction organization design

6) Technical and safe delivery

7) Pile level measurement release line record

8) Engineering positioning measurement discharge line record

9) Commencement report

10) Construction records

11) Construction log

12) Basic acceptance report, pre-acceptance record

13) Drawing triage record

14) Test pile records

15) Summary table of prefabricated pile certificates

16) Welding wire certificate

17) Precast pile entry acceptance record

18) Pile deviation acceptance record

19) Foundation groove inspection record

20) Pile foundation sub-division engineering quality acceptance record

21) Process handover inspection record

22) Quality acceptance records of sub-project inspection batches

23) Sub-project quality acceptance record

24) Construction plan

25) Unit engineering quality control data verification records

26) Pile foundation test report

The information to be submitted for the acceptance of the main structure of the project

1. Structural entity information

1. Drawing triage record

2. Quality and safety supervision and submission records

3. Foundation processing data

4. Foundation groove inspection record

5. Foundation pile test report

6. The most acceptance report of the engineering quality of the main structure division

7. Inspection report of anchoring resistance after reinforcement

8. Cement factory qualification certificate and entry inspection report

9. Brick factory qualification certificate, entry inspection report

10. Steel factory qualification certificate, entry inspection report

11. Steel connection test report, welding rod (agent), connection factory certificate

12. Concrete and mortar mix ratio notice, sand and stone inspection report

13. Concrete test block test report, concrete impermeability test report

14. Concrete condition maintenance test block test report

15. Mortar test block test report

16. Concrete and mortar strength evaluation table

17. Settlement observation records

18. Steel reinforcement protective layer test report and treatment opinions

19. Plate thickness checklist

20. Design change notice, engineering and technical approval form, material substitution visa form

21. Notice of suspension and resumption of work and rectification completion report

22. Quality problem (accident) processing data

Acceptance of the basic and main structure, and summary of the data that the supervisor needs to prepare

2. Information on the conduct of the responsible entities of each party to the project construction

Construction

1. Qualification certificate of real estate development company

2. Construction project quality and safety supervision certificate

3. Construction permit for construction projects

4. Construction Project Planning Permit (Notice)

5. Contract for entrusted supervision of construction projects

6. Construction drawing design document review opinions and design reply opinions

7. Approval of construction drawing design documents for construction projects

Survey and design units

1. Unit qualification

2. Enterprises outside the province shall be registered in the local area for the record

Supervisory unit

2. Registration of foreign supervision companies

3. Project supervision qualification review form

4. Director, supervision engineer, supervisor induction certificate

5. Construction project quality and safety ability assessment certificate

6. Supervision planning and supervision rules

7. Side station supervision plan, side station supervision record

8. Review of safety technical measures, special plans, entry materials, equipment, and visa materials designed by the construction organization

9. Supervision log (quality, safety issues and processing results should be recorded)

Construction unit

2. Foreign construction enterprises enter the pan for filing and registration

3. Safety production license

4. Notice of winning the bid for engineering construction

5. Construction site management personnel qualification certificate (project manager, project technical leader, construction worker, quality officer, safety officer)

6. The main person in charge of the enterprise and the ability assessment certificate of the safety management personnel (legal person, project manager, safety officer)

7. Continuing re-education assessment certificate (project manager, safety officer, quality inspector)

8. Special operator operation certificate: lifting machinery operation (driver, commander, division), electrical work, metal welding (cutting) operation, building ascent and erection operation, etc

9. Construction organization design, special construction plan (high slope, deep foundation pit, scaffolding, formwork, tower crane, lindian, etc.).

10. Construction of lifting machinery and overall lifting scaffolding, formwork and other jack-up erection facilities for the record and testing.

11. Accident insurance

12. Emergency rescue plan for production safety accidents.

13. Safety bottoming, inspection and acceptance records (foundation pit support, scaffolding, tower crane, tall formwork, power).

14. Safety evaluation letter

15. Construction project inspection batch, sub-project, branch (sub-division) project quality acceptance record.

16. Hidden project quality acceptance record

17. Supervise the submission of records

The conditions that should be met for the acceptance of the main structure

1. Each sub-project of the main structure division should be completed according to the design documents and meet the requirements of the construction quality acceptance specification.

2. Quality assurance data, the quality behavior data of the responsible entities of all parties involved in the construction have been reviewed and complete, and meet the requirements (the data should be reported to the Supervision Department for review five days in advance).

3. The problems raised in the rectification notice must be fully handled and meet the requirements.

4. The test of the steel reinforcement protection layer of the cast-in-place concrete component is qualified (if it is necessary to deal with it, there should be a design verification order or processing opinion and a complete signature and seal).

5. The construction site meets the conditions of civilized construction safety production, and the safety evaluation in the decoration stage is qualified.

6. The door and window frames must be installed in place according to the design and specification standards.

7. When the thickness of the junction of different materials and the plaster layer ≥ 35mm, the measures to prevent wall cracking must be all set in place (add steel wire mesh, the width of each side ≥ 100mm).

8. The lock ring in the junction box must be fully set in place.

9. The floor with waterproof requirements must be set with c20 concrete flanges with a height of ≥ 120mm and a width of the same width as the wall except for the door opening.

10. The thickness of the floor slab (each) must be fully measured and approved by the supervising engineer to form a signed inspection record.

Information to be submitted for the completion and acceptance of the project

1 Engineering quality assurance system review form

2 Drawing triage minutes

3 Foundation groove inspection records

4 Foundation and pile test report

5 Foundation and foundation division project quality acceptance report

6 Main structure division engineering quality acceptance report

7 Construction engineering foundation branch acceptance filing form

8 Acceptance filing form of the main branch of the construction project

9 Construction Engineering Division (Professional) Project Acceptance Filing Form

10 Construction project single (subsidiary) project acceptance filing form

11 Security door certificate and performance test report

12 Waterproof engineering impermeability test records and waterproof materials certificate, inspection report

13 Backfill soil compactness test report

14 Pipeline hydrostatic test records

15 System (domestic feed water) disinfection and cleaning records

16 Insulation test records

17 Grounding (lightning protection, protection) resistance test records

18 Decoration project cement entry inspection report

19 Decoration engineering material test report

20 Building exterior wall finish brick bond strength test

21st floor ground engineering mortar (concrete) test block strength report

22 Application report for completion and acceptance of construction projects (unit projects).

23 Project Quality Assessment Report

24 Design document quality inspection report

25 Opinion on Fire Acceptance of Construction Projects

26 Indoor environmental pollution test report of civil construction projects

27 "Approval Document" issued by the environmental protection department

28 Construction safety evaluation certificate for construction projects

29 Approval of construction drawing design document review

30 Submit to the planning department for inspection and issue "Completion Approval Document"

31 Construction Enterprise Quality Management Evaluation Manual

32 Household Checklist

The simple request is

Construction Party:

The acceptance record of the main branch project, the acceptance record of each sub-item, the quality acceptance record of each inspection batch, the report of the main strength test block assessment (including concrete and mortar), the inspection report of the solid strength (concrete and masonry), the inspection report of the steel protection layer, the thickness test of the concrete slab, and the summary of the main construction.

Supervising Party:

The summary of the main body supervision and the quality assessment report of the main project