East Taihu Lake Resort (Taihu New Town).
Hengli Suzhou Bay Environmental Enterprise Center Phase V Project
The main structure was successfully capped
Marks
Significant progress has been made in the construction of the project
The fifth phase of the tower of the Environmental Enterprise Center is used as
Super high-rise commercial office building
Total floor area
194,000 square meters
There are three underground floors and fifty-one floors above ground
The depth of the foundation pit is 15 meters
Building height
197.07 U.S.
Since March 2022 project
Since the official start of construction
The project has always been maintained
Good momentum for rapid progress
It lasted 25 months
Reach the cap node
Project Manager Wang Bin said:
We focused on breaking through the 8.7-meter layered backfill brick membrane pit construction in the pit, the construction quality control of the large-volume ultra-thick foundation floor, the beam-column node core column reinforcement connection technology under complex working conditions, and the overall basement sub-regional staggered cross construction organization.
It is understood
Hengli Suzhou Bay Environmental Enterprise Center Project
Total floor area
1.27 million square meters
contain
In order to seize the construction period
The whole project is divided into six bids
Construction started at the same time
As of now
It's done
Construction of about 1.22 million square meters
The entire engineering structure is completed in progress
96%