The 240,000-square-meter Jinjun Plaza is expected to open in April next year

author:Yunnan loushi

Many doubts and speculations about the progress of the Spring Eye project are obviously ignoring the changes in the façade of the commercial podium of the first phase of the Spring Eye, and the project progress made such rumors even more self-defeating on November 27 in the face of the city's media real scene.

The 240,000-square-meter Jinjun Plaza is expected to open in April next year

Entering the spring eye site site, it can be seen that the façade of the first phase of the commercial podium with the core intention of "Spring Wind" has been installed on a large scale, including 8,000 square meters of white color glazed glass folding glass curtain wall, and 3,000 square meters of wood grain color glazed glass curtain wall east and west facades, a total of more than 5,000 kinds of color glaze groups, and the use of the world's most advanced mesh board "color printing" technology, with lighting, forming a "breeze, blowing spring grass and trees" Building façade flow sense.

The 240,000-square-meter Jinjun Plaza is expected to open in April next year

The main entrance of the north façade adopts a glass ribbed all-glass curtain wall, the height of the glass curtain wall is 16 meters, the glass rib adopts 19+19+19mm thick ultra-white laminated glass, and the top glass adopts 12+12+12mm thick ultra-white laminated glass, which reflects a full sense of science and technology under the premise of meeting the transparent and clean aesthetic premise.

The 240,000-square-meter Jinjun Plaza is expected to open in April next year

It is understood that the first phase of the Spring Eye commercial podium was designed by Callison RTL, a world-renowned commercial design unit that has operated through Shanghai Plaza 66, Yintai Center, Shuncheng Wangfujing, and many China Resources Centers in China, creating an elegant and stretched architectural form that meets the regional characteristics of "Spring City" Kunming.

The 240,000-square-meter Jinjun Plaza is expected to open in April next year

In addition to the forward-looking and humanized building façade modeling, the construction of the first phase of the Spring Eye Commercial Center is also being carried out in an orderly manner. According to the person in charge of the project, at present, the first phase of the Spring Eye commercial center is undergoing comprehensive fine decoration construction, of which the model section of the toilet wall masonry and keel installation have been completed, the ceiling comprehensive installation has been completed, and the end of the sprinkler branch pipe is being chased.

The 240,000-square-meter Jinjun Plaza is expected to open in April next year

In addition, the INSTALLATION OF THE GRC in the large atrium was completed, the production of the ceiling modeling of the elevator was in progress, the scaffolding of the large atrium of the public area was erected, the secondary fire protection transformation of the ceiling top surface of each floor was carried out, the welding of the skull frame of the door of the wall shop and the pre-embedding of the ground floor pipeline were underway.

The 240,000-square-meter Jinjun Plaza is expected to open in April next year

In terms of mechanical and electrical engineering, the overall completion of the mechanical and electrical installation of the first phase of the Spring Eye Commercial Center has reached 95%, the fire control acceptance of the B01-9 floors has been completed, and the floors have been connected with water and electricity. The main HVAC, conventional water and electricity, fire protection systems, gas, elevators, etc. have been installed, and intelligent system installation is underway. At this stage, it is mainly coordinated with hardcover adjustment of mechanical and electrical pipelines and terminals, as well as the commissioning of major systems.

The 240,000-square-meter Jinjun Plaza is expected to open in April next year

With the steady progress of various engineering construction work, the project said that the first phase of the Spring Eye Commercial Center is expected to usher in the model section review at the end of December, and the small owners of the shopping mall can be arranged to enter the decoration, which is expected to be completed at the end of April 2022, when the "Jinjun Plaza" jointly built by Junfa and Ginger will be officially opened.

The 240,000-square-meter Jinjun Plaza is expected to open in April next year

Jinjun Plaza is the first phase of the Spring Eye podium commercial, with a total construction area of about 240,000 square meters, including underground B5 floors and local 9 floors, after opening will introduce internationally renowned luxury brands, beauty, tide brands, catering, retail, high-end life supermarkets, nail salons and other diversified formats.

The 240,000-square-meter Jinjun Plaza is expected to open in April next year

The second phase of the project is a 308-meter south tower, a total of 71 floors, which will create an urban large flat-floor apartment; the 77-storey north tower containing office buildings, apartments and ultra-luxury five-star hotels is the third phase of the project, and the building height of 407 meters after completion will also refresh the skyline of Kunming and even Yunnan.

The 240,000-square-meter Jinjun Plaza is expected to open in April next year

It is precisely because of the landmark height of the kunming center that the development difficulty of the "super project" of the Eye of Spring is constantly breaking the Yunnan record, but such a magnificent, elegant, humble, fashionable and restrained top work, which will represent the highest prosperity of the Kunming era, is naturally worth the city's time to wait.